What role focuses on ensuring appropriate ownership of risks relating to external events beyond the boundaries of the programme?
A. Risk owner
B. Programme Manager
C. SeniorResponsibleOwner
D. Risk actionee
Which of the following statements about the core elements of successful communications is true?
1.
Stakeholder analysis is required
2.
Audit trail is established
A. Only 1 is true
B. Only 2 is true
C. Both land 2are true
D. Neither 1 or 2 is true
Which describes the result of a risk on a programme?
A. Risk cause
B. Risk appetite
C. Risk aggregation
D. Risk effect
Which activity includes addressing the disadvantages of `doing nothing' to those stakeholders that object to the programme?
A. Analyse stakeholders
B. Sum ma rise risks
C. Carry out a health check
D. Conduct a visioning workshop
Which is a reason for Benefits Management continuing beyond the end of the programme?
A. Other benefits have to be realized, but will need to be owned and managed to pre- agreed target levels that are yet to be achieved
B. The Business Change Team's benefit responsibilities need to be re-allocated due to a number of members leaving the organization
C. The Benefits Map has been redrawn as a result of a change to the strategic objectives of the organization
D. A business assurance review is needed to ensure capabilities are being embedded and benefits measured
Why are programme governance baselines updated?
A. Reflect lessons learned, in Managing the Tranches
B. Adjust programme governance to align with project governance, in Delivering the Capability
C. Reflect lessons from earlier programmes, in Identifying a Programme
D. Prepare for benefit reviews, in Realizing the Benefits
What role, in approving the design of the programme, has a focus on compliance with corporate controls?
A. Programme Office
B. Programme Manager
C. Senior Responsible Owner
D. Business Change Manager
Which is a purpose of the Programme Office?
A. Create new working practices for business operations
B. Write new versions of information baselines
C. Provide programme information services
D. Ensure stakeholders have access to all programme documentation
Which is a responsibility of the Programme Manager?
A. Approves programme's progression to next tranche
B. Defines risk thresholds for the programme's projects
C. Ensures appropriate programme assurance is in place
D. Reports regularly on programme progress
Which management experience would BEST enable a member of a Business Change Team to fulfil their responsibilities?
A. Transition
B. Project
C. Risk
D. Portfolio
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MSPF exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.