  • Question 31:

    There are 100 units of an item on hand. A user enters a sales order for 40 units with a delivery date in 20 days.

    Why would Master scheduling create a planned purchase order to cover the sale, instead of using the existing inventory?

    A. Negative days is less than 20.
    B. Positive days is less than 20.
    C. The firming time fence is less than 20.
    D. The coverage time fence is less than 20.

  • Question 32:

    Which Master plan parameter is only used with job scheduling?

    A. Finite capacity
    B. Finite property
    C. Bottleneck scheduling
    D. Reduction principle

  • Question 33:

    Which of the following are possible job types in the route group? Choose the 2 that apply.

    A. Queue before
    B. Phantom
    C. Setup
    D. Subcontractor

  • Question 34:

    How is an item coverage planned if it does not belong to a coverage group and no item coverage is defined?

    A. The item is not coverage planned.
    B. The item is coverage planned according to the default coverage group given in the\ Master planning parameters.
    C. The item is coverage planned according to the default coverage group given in the setup of the Master plan being used.
    D. The item is coverage planned according to the default coverage group defined in the Inventory management parameters.

  • Question 35:

    Without selecting "accept error", when can a production order be reported as finished?

    A. When reporting on the last operation from a route or job card journal.
    B. When reporting on any operation from a route or job card journal.
    C. When reporting on the first job on the work center.
    D. When releasing the production.

  • Question 36:

    A company can use scheduling strategy that uses one master plan or multiple master plans. When should a company use a strategy with one master plan?

    A. When the company wants to make sales order simulations.
    B. When the company wants to calculate exact delivery dates.
    C. When it is not important that sales people can confirm delivery dates to customers.
    D. When orders resulting from order simulations are not firmed right away.

  • Question 37:

    What occurs if a production order is released, but has not been estimated or scheduled?

    A. The estimation and scheduling steps are skipped.
    B. The estimation and scheduling steps are performed automatically.
    C. The status is reset to 'Started.'
    D. An error message displays and you must complete the estimation and scheduling steps manually.

  • Question 38:

    A sales order with a delivery date in 90 days, for an item using the requirement coverage code, is not covered by a planned purchase order when Master scheduling is run. Why is the sale not requirement covered?

    A. Firming time fence is less than 90 days.
    B. Action time fence is less than 90 days.
    C. Capacity time fence is less than 90 days.
    D. Coverage time fence is less than 90 days

  • Question 39:

    When can a production order be split?

    A. It can only be split when its status is Created.
    B. It can be split up until the total scheduled quantity is started.
    C. It can be split once and this must be done prior to Job scheduling.
    D. Itcan be split once and this must be done prior to Operation scheduling.

  • Question 40:

    You need to produce a prototype item similar to an existing item you currently produce. The new prototype item will be the same as the existing item, but will have one half the quantity of one of the BOM components. How can you efficiently produce the prototype item using the BOM from the existing item with the least impact to the existing BOM? Choose the 2 that apply.

    A. Modify the BOM for the existing item, select the BOM to produce the prototype item, then modify the BOM again back to the original.
    B. Create the production order and select the BOM for the existing item then edit the BOM from the production order.
    C. Use the BOM for the existing item and create a picking list with the correct quantity of BOM items.
    D. Use the BOM for the existing item and change the production order quantity to half the quantity required.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MB6-822 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.