You are the production supervisor in charge of setting effective cost prices for the labor force in a manufacturing company.
It is the end of the year and the labor rates have been recalculated based on new salary data.
You need to update the effective labor costs for all labor groups.
Which element must be updated?
A. cost groups
B. shared category
C. resource group
D. cost category
E. production orders
A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer
lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
A. Configure the Data/Hour option on the Capacity unit field on the resource.
B. Build capability related to length and assign to the appropriate resources.
C. Create a resource group for each length.
D. Create a resource for each length.
A company manufactures and sells speaker boxes. The speaker boxes can be silver or black with a basic or upgraded wiring harness assembly.
The speaker box must be created in the item master so the variables for colors and harness type can be assigned at order entry.
You need to create a new item that supports multiple variables.
What should you do?
A. Create a new product. Select predefined variant as the configuration technology
B. Create a new product. Select constraint-based configuration as the configuration technology
C. Create a new product master. Select predefined variant as the configuration technology
D. Create a new product master. Select constraint-based configuration as the configuration technology
You are the production supervisor at a chemical processing plant. You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished.
You need to ensure that the values of attributes are updated and tracked.
What three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A. Assign the attributes to the chemicals
B. Assign the attributes to the appropriate test on the test group
C. Create attribute types
D. Set up batch attributes
E. Create a test instrument for each attribute
A manufacturer produces HDMI cables. Typically, the item is manufactured.
The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.
What should you do?
A. Select route type as vendor on the route operation when the item is to be purchased.
B. In default order settings, select Production for the default order type
C. Create a new vendor resource when the item is to be purchased
D. In default order settings, select Purchase for the default order type
A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents part of solution.
NOTE: Each correct selection is worth one point.
A. Enter a value in the queue time after field for the painting operation
B. Make a resource group for each size and color and assign that group to the operation
C. Enter a value in the transit time on the painting operation
D. Enter a value in the queue time before field for the assembly operation
E. Build capabilities for each resource related to color
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
A. Navigate to the resource group. Change the calendar to closed on the resource group.
B. Navigate to the calendar used for production and close the next two days.
C. Navigate to the resource. Change the calendar to closed on the resource.
D. Navigate to the resource and select Calendar deviations. Set the calendar to closed for the next two days.
A manufacturing company is implementing Dynamics 365 Supply Chain Management. The company uses a standard costing model to value inventory.
During the setup of the system, all areas that impact the standard cost of the item must be configured correctly to calculate a complete standard cost by using routing, Bill of materials (BOM) and overhead burden.
You need to verify that all areas of the system are correctly configured.
Which object does NOT impact the standard cost of manufactured items?
A. item group
B. cost groups
C. cost categories
D. BOM formula
A company is looking to use Dynamics 365 Supply Chain Management.
The company is in the process of redesigning and retooling an existing manufacturing plant to group similar, cellular operations to improve efficiency and minimize wasted time between operations. They want to locate raw materials close to
where they are needed without losing reorder visibility.
You need to set up their environment.
Which kind of production type should you implement?
A. Lean manufacturing
B. Process manufacturing
C. Discrete manufacturing
D. Manufacturing execution
A company is looking to use Dynamics 365 Supply Chain Management.
The company is in the process of redesigning and retooling an existing manufacturing plant to support a large long-running contract. They want to be able to forecast capacity to easily ramp up for additional products.
You need to set up the environment.
Which type of manufacturing should you implement?
A. Lean
B. Discrete
C. Job shop
D. Process
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MB-320 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.