  • Question 121:

    Which of the following statements does NOT describe good practice for maintaining the TAS?

    A. The TAS must run in the development environment because development and programming knowledge are required for its maintainability
    B. The TAS must be under configuration management, along with the test suite, the testware artefacts and the test environment in which it runs
    C. The TAS must separate the test scripts from the environment in which it runs and from the associated harnesses and artefacts
    D. The TAS must consist of components that can be easily replaced without affecting the overall behavior of the TAS itself

  • Question 122:

    When designing a TAA, which of the following is NOT a technical design consideration?

    A. Availability of interfaces that make the SUT testable
    B. Standards and legal requirements such as data privacy
    C. Data used by the SUT, such as configuration or user data
    D. The number of end users who will use the SUT in production

  • Question 123:

    You are working on a web-based application called Book Vault that allows people to upload books and order books. This application must be available on all major browsers. You have been testing the application manually and management have asked you to consider automating some of the tests.

    You have investigated a number of commercial and free tools which can automate tests at a web browser level and one tool in particular meets your requirements and you have implemented a trial version. You have basic programming skills and the main goal is to automate a few functional tests to see if the tool is compatible with the application and can recognise the objects and controls.

    Which scripting technique would be MOST suitable in this scenario in order to meet the objectives?

    A. Structured scripting
    B. Capture-replay scripting
    C. Data-driven scripting
    D. Model-based scripting

  • Question 124:

    A SUT has an existing automated test suite.

    Which of the following statements relating to the introduction of new features in the SUT is TRUE?

    A. Automated tests are not affected by the introduction of a new feature and running them against the new SUT is a waste of effort
    B. The introduction of a new feature could require updates or additions to the testware components
    C. The test automation engineer should work with the business analysts to ensure the new feature is testable
    D. It is generally more difficult to automate test cases for a new feature as the development has not yet started

  • Question 125:

    Assume that you are working on a TAS for standalone desktop applications. The automated tests are developed based on a given automation framework that allows interacting with the application using the GUI elements by means of an object-oriented API. The TAS needs also a tool that allows identifying the properties of these elements. In this tool the root element represents the current desktop and the child elements represent application windows. Each of these child elements contains GUI elements (e.g., menus, buttons, radio buttons, text boxes, toolbars etc.) with their properties. Unfortunately, the elements of two third party components are not unidentifiable by this tool and thus they cannot be used with the specified framework.

    Based only on the given information, which of the following is the first step that you should consider to address such issue in this scenario?

    A. Verify the testability support within the current automation solution with the providers of the third party controls
    B. Verify whether the identifiability issue associated to the third party controls depends on the web browser
    C. Adopt an approach that uses the coordinates of the GUI elements for interacting with the application
    D. Verify whether naming standards for variables and files have been defined for the current automation solution

  • Question 126:

    You are the TAE for an Agile project which has six sprints for the current release. Sprint five is underway and the automated regression suite is due to start later today. You have re-examined the results from the automated regression runs for the past four sprints. You notice that two test cases both reported a pass for sprints 1 and 4 but a fail for sprints 2 and 3. The failures have gone undetected and are therefore unexplained. Both test cases are closely coupled with other tests in the suite.

    What course of action SHOULD you take?

    A. Run the regression suite as planned and see If the tests fail again if they do, determine the cause of failure.
    B. Remove the test cases from the regression suite and refer them to the test designer for manual testing for future sprints.
    C. Quarantine the test cases, run the regression suite without them, and perform root cause analysis on the test cases in parallel.
    D. Run the test cases manually now. If they still pass, keep them in the regression suite, if they fail perform root cause analysis.

  • Question 127:

    You have been running an automated test suite over the last several months, but you are seeing intermittent failures. Further analysis has determined that the failures are caused by data issues. The test data is replicated from production and periodically changes. The scripts are supposed to be flexible enough to handle the data changes, but they are not.

    At this point, what should you do?

    A. Further analyze the failures so the problems can be provided to the developers.
    B. Comment out the tests that have the intermittent failures so the pass/fail metrics won't track the false negatives.
    C. Investigate ways to control the test data either by generating it or by checking it before use to improve repeatability of the test results.
    D. Manually test each failing test to verify the failure and to understand how to recode around the failure.

  • Question 128:

    You have been asked to automate a set of functional tests at system Test level via the CLI of the SUT for the first release of a software system. The automated tests will be delivered to the learn in change of maintenance testing, who will use them for part of the regression testing. They have the following requirements.

    1. The automated tests must be as fast and cheap to maintain as possible.

    2. The cost of adding new automated tests must be as low as possible.

    3. The automated tests must have a high level of independence from the tool itself.

    Which of the following scripting techniques would be MOST suitable?

    A. Data-driven scripting
    B. Keyword-driven scripting
    C. Linear scripting
    D. Structure scripting

  • Question 129:

    Which of the following is considered a disadvantage of test automation?

    A. Automated exploratory testing is difficult to implement
    B. Test automation can be a distraction from the objective of finding bugs
    C. Tests are more likely to have operator errors.
    D. Slower feedback on the quality of the system.

  • Question 130:

    You are using a gTAA to create a TAS for a project. The TAS is aimed at automatically and executing test cases based on a use-case. Modeling approaching that uses UML as a modeling language. All the interaction between TAS and SUT will only be at the API and GUI level.

    Which of the following components of the gTAA would you EXCLUDE from the TAS?

    A. The test reporting component of the test execution layer.
    B. The Test execution component of the test generation layer
    C. The test execution (test engine of the test execution layer
    D. The Command Line Interface (CLI) component of the test adaptation layer

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISTQB-CT-TAE exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.