ICYB Exam Details

  • Exam Code
    :ICYB
  • Exam Name
    :IASSC Certified - Lean Six Sigma Yellow Belt
  • Certification
    :IASSC Certifications
  • Vendor
    :IASSC
  • Total Questions
    :151 Q&As
  • Last Updated
    :Jul 11, 2026

IASSC ICYB Online Questions & Answers

  • Question 1:

    A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:

    Data:

    Trimming

    37

    Forming

    61

    Packaging

    29

    Sealing

    5

    A. Trimming, Packaging, Sealing, Forming
    B. Packaging, Trimming, Sealing, Forming
    C. Sealing, Forming, Trimming, Packaging
    D. Forming, Sealing, Trimming, Packaging

  • Question 2:

    Six Sigma refers to a process whose output has at least 75% of its data points within 6 Standard Deviations from the Mean.

    A. True
    B. False

  • Question 3:

    A Monitoring Plan put into place at the conclusion of a project will provide for adequate systems with key metric readouts indicating out-of-spec conditions.

    A. True
    B. False

  • Question 4:

    The ROI for a project is a measurement metric that stands for Return on Investment and is one of the methods used to measure the success of a Lean Six Sigma project.

    A. True
    B. False

  • Question 5:

    The purpose of ________________ is to analyze data and present it in a way we can make informed decisions as to what is happening in our process.

    A. Data Sampling
    B. Basic Statistics
    C. Calculating Standard Deviation
    D. Measurement System Analysis

  • Question 6:

    Measurement System Analysis is a procedure used to quantify variation of the method or system used for taking measurements and used to assure usable data is collected.

    A. True
    B. False

  • Question 7:

    One method of implementing control to the critical phase of a process is to automate the stoppage of the process if a key metric goes out of specification. This control tool is called ___________________.

    A. Process Interruption
    B. Poka-Yoke
    C. Spec Stop
    D. Flow Protection

  • Question 8:

    A Monitoring Plan put into place at the conclusion of a project will provide for adequate systems with key metric readouts indicating out-of-spec conditions.

    A. True
    B. True

  • Question 9:

    A Belt has determined that the loan application does not need to be reviewed by accounting thereby improving the number of applications a loan processer can handle. According to Cost of Poor Quality (COPQ) definitions RTY improvement would be considered _______________.

    A. Downsizing savings
    B. Hard savings
    C. Soft savings
    D. Median savings

  • Question 10:

    One of the 5S approaches to eliminating waste is to minimize work activities that are out of the ordinary thereby requiring unusual decisions and actions to accomplish the correct things. This 5S tool is called __________________.

    A. Standardizing
    B. Scheduling
    C. Sustaining
    D. Sorting

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IASSC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ICYB exam preparations and IASSC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.