  • Question 1:

    A customer is planning an HPE Synergy solution with 20 frames and needs to minimize the number of management ports that are required to connect the frames into the existing management network.

    Which procedure should the Synergy integrator use to address the customer's concern?

    A. Connect FLMs from all frames into a management ring. Then connect the management ring to the customer's management network using two uplinks.

    B. Connect FLMs from all frames to two external switches for redundancy. Then connect the two uplinks from the two switches into the customer's management network.

    C. Connect the RJ-45 front ports of each frame to two external switches for redundancy. Then connect the uplink from the two switches into the customer's management network.

    D. Connect the RJ-45 front ports of each frame to an external switch. Then connect the uplink from the external switch into the customer's management network.

  • Question 2:

    Using a laptop, how can the Synergy integrator perform the initial setup on an HPE Synergy 12000 Frame?

    A. Connect a CAT5 cable to the front panel module, use the HPE Synergy default IP address of 192.168.10.31, port 5900, and connect to the HPE Synergy console with VNC.

    B. Connect a CAT5 cable to the MGMT port of the top Frame Link Module and connect to the HPE Synergy console with VNC to the address 248.196 port 5900.

    C. Connect a CAT5 cable to the front panel module, use the HPE Synergy default IP address of 192.168.10.1, port 5900, and connect to the HPE Synergy console with a web browser.

    D. Connect a CAT5 cable to the MGMT port of the top Frame Link Module and connect to the HPE Synergy console with a web browser to the address 192.168.10.1, port 5900.

  • Question 3:

    Which component of the HPE Synergy solution enables fast OS deployments to compute modules?

    A. HPE Synergy Frame Link

    B. HPE Synergy Image Streamer

    C. HPE Synergy Composer

    D. HPE Synergy Compute

  • Question 4:

    A customer need four Synergy compute nodes to provide virtual machine access to six VLANs over a single link aggregation group.

    How can the Synergy integrator configure the environment to meet the customer's needs?

    A. Create a single tunnel network and assign it to one or more interfaces in the server profile template.

    B. Create six untagged networks and assign them to one or more of the interfaces in the server profile template.

    C. Create six untagged networks, associate them with an IP address pool, and assign them to one or more of the interfaces in the server profile template.

    D. Create six untagged networks, add them to a network set, and assign that network set to one or more interfaces in the server profile template.

  • Question 5:

    A customer has the following configuration:

    15 Synergy Frames with 150 HPE SY 480 Gen9 compute modules

    15 HPE Synergy D3940 storage modules with 40 disks each

    10 Image Streamers

    10 HPE Synergy Virtual Connect SE 40Gb F8 modules

    20 20Gb Interconnect Link Modules

    During setup, how many enclosures should the Synergy integrator select for the Logical Interconnect Group ((LIG)?

    A. 5 enclosures

    B. 10 enclosures

    C. 15 enclosures

    D. 20 enclosures

  • Question 6:

    A customer is unable to boot to a 3.5TB volume created and presented to a compute node.

    What is likely preventing the boot?

    A. Boot volumes larger than 3TB are not supported on HPE Synergy.

    B. The system is set to Legacy BIOS mode instead of UEFI.

    C. The system is set to UEFI instead of Legacy BIOS mode.

    D. Boot volumes larger than 2.2TB are not supported on Synergy.

  • Question 7:

    A Synergy integrator is working with a customer to perform a first-time setup of a 3-frame Synergy environment. The following fabric modules are installed: Frame 1

    Bay 1

  • Question 8:

    A customer has forgotten the password for the HPE OneView Appliance controlling the customer's HPE Synergy Infrastructure.

    Where can the customer reset the password with the assistance of HPE Support?

    A. Maintenance Console screen

    B. FLM Access to Synergy Console

    C. Virtual Center server

    D. Front Access Panel to Synergy Console

  • Question 9:

    A Synergy integrator needs to add more NICs to a server profile.

    What does the integrator need to be aware of when performing this action?

    A. The host needs to be powered off to activate the change.

    B. The Virtual Connect modules need to be rebooted once the profile is applied.

    C. The server profile template must be changed before modifying the server profile.

    D. The host networks will go offline when the profile is assigned.

  • Question 10:

    What should a Synergy integrator do to resolve an unresponsive HPE Synergy Frame Link Module?

    A. Press the reset button on the front of the HPE Synergy Frame.

    B. Remove and reinstall the Frame Link Module in the original bay.

    C. Remove and reinstall the Composer.

    D. Disconnect and reconnect the Frame Link Module from the management network.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only HP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your HPE0-S50 exam preparations and HP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.