  • Question 31:

    What is the best way to split up teams on a large project which is implemented using Scrum?

    A. Group by domain expertise.
    B. Group by features being developed,
    C. Group by specialty of the team members.

  • Question 32:

    When is a Sprint complete?

    A. When all of the Product Backlog items are completed.
    B. When all the tasks in the Sprint Backlog are completed.
    C. When the Sprint defined time box ends.

  • Question 33:

    A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint. What is the most likely reason that the team did not meet the Sprint objectives?

    A. The Product Owner is unable to prioritize.
    B. The team is lacking skills.
    C. The team did not plan the Sprint effectively.
    D. The team is over-worked.

  • Question 34:

    What should the Scrum Master advise the team to give their main focus, while working in a global distributed team?

    A. Favor conference calls and video chats in order to save on travel budget.
    B. Place greater emphasis on team-building activities and cultural sensitivities.
    C. Provide at least four hours of overlap time by changing working hours.

  • Question 35:

    How does Agile bring predictability to the Planning process?

    A. By allowing the customers to review the progress often.
    B. By assigning most of the responsibility to the Product Owner.
    C. By making the team self-organized and self-planning.
    D. By providing early visibility into the team's progress.

  • Question 36:

    Sprint duration is usually fixed at one month or less. Why is that?

    A. Because customers cannot wait longer than a month.
    B. Because it is difficult to focus on the same thing for longer.
    C. Because this keeps the complexity and risk acceptable.

  • Question 37:

    Who is accountable for a task that is assigned to a single Team member?

    A. The Product Owner
    B. The Scrum Master
    C. The Development Team
    D. The single Team member

  • Question 38:

    What is the usual length of the time box for the complete Sprint Planning meeting?

    A. Four hours for a 30 day Sprint, one to two hours for a shorter Sprint.
    B. However long it takes to complete the Sprint Backlog.
    C. Never more than two hours, regardless of Sprint length.

  • Question 39:

    A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story?

    A. 1.25 days
    B. 1.33 days
    C. 2 days
    D. This cannot be determined without knowing the velocity.

  • Question 40:

    Which Scrum ritual is meant to look back and improve upon the finished Sprint?

    A. Daily Scrum.
    B. Sprint Retrospective.
    C. Sprint Review.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EXIN-ASF exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.