  • Question 81:

    Which is a purpose of a Lessons Report?

    A. Improve the project management method for future projects
    B. Detail open issues and risks that need to be managed after the project has closed
    C. Compare the actual performance of the final stage against its plan
    D. Provide a summary of the benefits realized during the project

  • Question 82:

    Which is a purpose of a Configuration Management Strategy?

    A. Provide a record of each configuration item and any important relationships between them
    B. Define how the products and their versions will be identified
    C. Define whether a project will use a risk budget
    D. Identify who will set up the Quality Register

  • Question 83:

    If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

    A. Senior User
    B. Executive
    C. Corporate/programme management
    D. Senior Supplier

  • Question 84:

    Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

    A. Defined roles and responsibilities
    B. Learn from experience
    C. Manage by exception
    D. Focus on products

  • Question 85:

    Which role is responsible for the management of a risk assigned to it?

    A. Project Support
    B. Risk owner
    C. Risk actionee
    D. Project Assurance

  • Question 86:

    Which is a purpose of a Project Brief?

    A. Enable the assembly of the project mandate
    B. Describe the reporting requirements of the various layers of management involved with the project
    C. Describe how changes to products will be controlled
    D. Provide a solid basis for the initiation of the project

  • Question 87:

    Which is a purpose of the Risk theme?

    A. Establish a method for the implementation of continuous improvement during the project
    B. Identify, assess and control problems that have occurred
    C. Provide the Project Board with a time-driven control to capture all project risks
    D. Establish a cost-effective procedure to identify, assess and control risks

  • Question 88:

    Which is an objective of the Controlling a Stage process?

    A. Prepare a Stage Plan for the next stage
    B. Obtain approvals for completed products
    C. Prevent scope creep' by monitoring products for uncontrolled change
    D. Make arrangements to address all open issues and risks, with follow-on action recommendations

  • Question 89:

    Which is NOT a type of issue?

    A. A problem/concern
    B. A constraint
    C. An off-specification
    D. A request for change

  • Question 90:

    Which characteristic distinguishes a project from regular business operations?

    A. Produces benefits
    B. Introduces business change
    C. Manages stakeholders
    D. Incurs cost

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.