  • Question 101:

    Which is a responsibility of a Team Manager?

    A. Producing Highlight Reports for the Project Manager
    B. Reviewing the status of the stage
    C. Setting Work Package tolerances
    D. Ensuring delivery of products in the Managing Product Delivery process

  • Question 102:

    Which is a purpose of the Plans theme?

    A. Identify, assess and control any potential changes to the baseline
    B. Establish the project's structure of accountability
    C. Assess and control uncertainty
    D. Understand whether the targets are achievable

  • Question 103:

    Which is a task of product-based planning?

    A. Design the plan
    B. Create the product flow diagram
    C. Analyze the risks
    D. Prepare the schedule

  • Question 104:

    How should the Team Manager report that tolerances are forecast to be exceeded?

    A. Create an Exception Report
    B. Create a Highlight Report
    C. Raise an issue
    D. Grant a concession

  • Question 105:

    Which is an objective of the Starting up a Project process?

    A. Approve all Product Descriptions prior to project initiation
    B. Obtain approval from corporate or programme management for the Communication Management Strategy
    C. Prevent projects with unrealistic delivery dates from being initiated
    D. Confirm that there is a valid method in place to measure the expected project benefits

  • Question 106:

    Which task is performed by the Change Authority?

    A. Set a change budget
    B. Approve or reject a request for change within approved limits
    C. Refer changes that exceed budgetary limits to the Project Manager for approval
    D. Update the configuration management system when a change is approved

  • Question 107:

    Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

    A. Change
    B. Plans
    C. Progress
    D. Risk

  • Question 108:

    Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

    A. producing an achievable Project Plan
    B. preventing poorly-conceived projects from ever being initiated
    C. obtaining approval from all stakeholders
    D. setting up the required project controls

  • Question 109:

    Which is a benefit of using PRINCE2?

    A. Provides a defined structure of accountability, delegation, authority and communication
    B. Includes techniques for critical path analysis and earned value analysis
    C. Enables a Project Manager to be accountable for the success of a project
    D. Prevents any changes once the scope of a project has been agreed

  • Question 110:

    What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

    A. Directing a Project
    B. Managing a Stage Boundary
    C. Controlling a Stage
    D. Starting up a Project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.