  • Question 111:

    Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

    A. Off-specifications
    B. Follow-on action recommendations
    C. Issue Register
    D. Risk Register

  • Question 112:

    Which role is responsible for specifying the project benefits?

    A. Corporate or programme management
    B. Executive
    C. Senior User(s)
    D. Project Manager

  • Question 113:

    Why is the Initiating a Project process used?

    A. To decide which project approach is suitable for the project
    B. To fully understand how the project objectives will be achieved before committing significant resources
    C. To produce the required Work Packages
    D. To enable corporate or programme management to give authorization to deliver a project

  • Question 114:

    Which provides a single source of reference that may be used by people joining a project after it has been initiated so they can quickly and easily find out how the project is being managed?

    A. Project Brief
    B. Project Initiation Documentation
    C. Project mandate
    D. Project Product Description

  • Question 115:

    Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

    A. Controlling a Stage
    B. Closing a Project
    C. Directing a Project
    D. Managing a Stage Boundary

  • Question 116:

    What process aims to ensure accurate progress information is provided to the Project Manager?

    A. Starting up a Project
    B. Managing a Stage Boundary
    C. Managing Product Delivery
    D. Directing a Project

  • Question 117:

    Which is an objective of the quality review technique?

    A. To identify a product's quality criteria
    B. To provide assurance that the project is being conducted properly
    C. To assess that a product conforms to set criteria
    D. To ensure that staff are properly trained in the quality methods

  • Question 118:

    Which is a purpose of a Risk Register?

    A. Capture risks that may occur during the project
    B. Record how risk management activities will be undertaken on the project
    C. Record the risk tolerance for the project
    D. Capture issues which are impacting on the delivery of the project objectives

  • Question 119:

    Identify the missing words in the following sentence.An objective of the Directing a Project process is to [?] throughout a project's life,

    A. document how risks will be managed
    B. identify who will be responsible for quality
    C. provide management direction and control
    D. define the benefits to be realized

  • Question 120:

    What is defined as a temporary organization that is created for the purpose of delivering one or more business products?

    A. Corporate or programme management
    B. A project
    C. A product breakdown structure
    D. A user group

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.