Question 1 Single choice

What do the small red triangles indicate in the below image?

  1. A

    The cells are locked and cannot be edited

  2. B

    The cells are editable

  3. C

    The cells data has been pasted by the Edit menu

  4. D

    The cells data is new data

Show answer and explanation

Correct answer: B

Question 2 Single choice

When saving a Route as template, the Scope opton is used to...

  1. A

    identfy who can use the template

  2. B

    identfy who can be added as members to the routes that will be created using that template

  3. C

    defne how the tasks can be assigned

  4. D

    identfy who can be owner of the route that will be created using that template

Show answer and explanation

Correct answer: A

Question 3 Single choice

What roles are authorized to create programs?

  1. A

    Only Program Leads and External Program Leads

  2. B

    Any role

  3. C

    Program designers only

  4. D

    Project leads only

Show answer and explanation

Correct answer: A

Question 4 Single choice

When creatng a Route, you can specify...

  1. A

    the order in which the tasks should be completed

  2. B

    the route member who should complete the task

  3. C

    whether the task assignee can delegate the task to someone else

  4. D

    all of these

Show answer and explanation

Correct answer: D

Question 5 Single choice

Which dependency code do you assign if the selected task CANNOT start untl the current task starts?

  1. A

    Finish-To-Finish

  2. B

    Finish-To-Start

  3. C

    Start-To-Finish

  4. D

    Start-To-Start

Show answer and explanation

Correct answer: D

Question 6 Single choice

When 2 people are assigned to the same task, the default allocaton is that...

  1. A

    both are set to 100%

  2. B

    each one is set to 50%

  3. C

    the 1st assigned person is set to 100% and the 2nd to 0%

  4. D

    both are set to 0%

Show answer and explanation

Correct answer: A

Question 7 Single choice

In the dashboard Image below, what is the red square indicatng?

  1. A

    The task is Complete

  2. B

    The task is not complete but not late or at risk

  3. C

    The task is a Milestone and is pending

  4. D

    The task is late

Show answer and explanation

Correct answer: D

Question 8 Single choice

In the image below what is "Line #1" indicatng?

  1. A

    Risk

  2. B

    Dependency

  3. C

    Current Time

  4. D

    Issue

Show answer and explanation

Correct answer: B

Question 9 Single choice

What does the green plus symbol represent in the below image?

  1. A

    Task was added using the Paste opton in the edit menu

  2. B

    Task was modifed using the Actons menu

  3. C

    One or more vales in the task were changed

  4. D

    Task was moved from another locaton in the structure for the same parent

Show answer and explanation

Correct answer: A

Question 10 Single choice

When you create a Project from a template, what method is used to determine what WBS tasks will be created?

  1. A

    Project Policy

  2. B

    Project Visibility

  3. C

    Questons assigned to tasks

  4. D

    Task Dependency

Show answer and explanation

Correct answer: C