  • Question 41:

    You have been asked to explain to your client how to define acceptance criteria that are fully testable. Which of the following is the BEST EXAMPLE for testable acceptance criteria?

    A. The ID field must accept input value of a length between 2 and 10 characters.
    B. The interface to External System shall be specified.
    C. Action Reopen must be available only for a user with a specific authorization level.
    D. The program's icon should be clear and attractive.

  • Question 42:

    Which one of the following is a testable acceptance criterion?

    A. The solution shall support business processes.
    B. The system shall be easy to use.
    C. The response time to confirm a customer submission must not exceed 5 seconds.
    D. The tools for testing are tested before use and are meeting the requirements.

  • Question 43:

    Which of the following describes a direct benefit of early and frequent feedback associated with the adoption of continuous integration?

    A. Detecting and isolating code quality problems early
    B. Reducing the need of conducting retrospectives
    C. Making quality everyone's responsibility
    D. Eliminating communication problems within the team

  • Question 44:

    An Agile team uses a burndown chart and a task board to track progress within each iteration. In the burndown chart, the x-axis represents the days of iteration, while the y-axis represents the story points. The task board uses columns: "To Do", "Ongoing", "Done".

    A user story for the current iteration has 20 story points and 4 tasks (T1, T2, T3, T4). At the end of Day 5, all are in "Ongoing". At the end of Day 6, T1 and T2 move to "Done", while T3 and T4 remain "Ongoing".

    Which of the following statements would you expect most likely to be true at the end of Day 6?

    A. The burndown chart should be updated with a number of 10 burned story points
    B. The burndown chart must be changed to represent the unit of work in hours because story points cannot be used
    C. The burndown chart should not be updated because T3 and T4 are not "Done" yet

  • Question 45:

    Which agile development approach incorporates the following practices:

    a project is divided into iterations called sprints

    each sprint results in a potentially releasable/shippable product?

    A. Kanban
    B. Extreme Programming
    C. Continuous Integration
    D. Scrum

  • Question 46:

    You have been asked to execute an exploratory testing session on Park and Ride system. The test charter has been titled as Buy a bus ticket. As a result, a number of defects were reported, the titles of which are listed below. Which defect is out of scope for the given test charter?

    A. Price for a bus ticket was calculated incorrectly.
    B. Failed to buy a bus ticket after 18:00.
    C. Failed to buy a bus ticket when the network connection to the Central System is down.
    D. Payment for parking ticket is restricted to cash only (no credit card supported).

  • Question 47:

    Which of the following statements about test automation and regression risk in Agile projects is true?

    A. Automated unit tests are generally not run with each code check-in as they take longer to run than automated acceptance tests and could slow down the code check-in process
    B. Regression risk is reduced when there is a high degree of code changes being applied from one iteration to the next
    C. Technical debt is due to manual testing and it cannot be present when the team implements test automation
    D. Test automation can help to manage regression risk since it allows the running of regression test suites within each iteration

  • Question 48:

    Which of the following is the BEST way for a test team to keep its independence when working in an Agile development environment?

    A. Share the Test Strategy with the Agile development team, but not the details of the Test Cases.
    B. Locate the team that develops the test automation framework in a different location to the Agile development team.
    C. Assign testers to be members of the Agile team, but ensure the testers report to a different manager than the developers.
    D. Co-locate only some of the testers with the Agile development team, while the rest of the testers are in a different location.

  • Question 49:

    Which of the following statements BEST reflects a key challenge of Agile regression testing?

    A. Regression tests never need maintenance
    B. Frequent changes increase regression risk
    C. Regression testing is unnecessary in Agile
    D. Regression testing is performed only once per release

  • Question 50:

    User Story: As a user I want to be able to calculate tax percentage based on amount of income. What is the best black box test design technique for verifying the accuracy of this user story?

    A. Statement testing - test all statements in income calculation.
    B. User story testing - test that the user can enter an income amount and get a result.
    C. State transition testing - test all states of income entry.
    D. Equivalence partitioning - test with low, medium and high income.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISQI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CTFL-AT exam preparations and ISQI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.