Question 1 Single choice

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

  1. A

    Methods of communication

  2. B

    The way the Scrum Team does Sprint Planning

  3. C

    Skills needed to improve the Development Team's ability to deliver

  4. D

    Its Definition of Done

  5. E

    All of the above

Show answer and explanation

Correct answer: E

Question 2 Single choice

Under what circumstances should separate Product Backlogs be maintained?

  1. A

    There are several Product Owners for one product. Each Product Owner should have their own Product Backlog

  2. B

    There are multiple teams working on independent products. Each unique combination of team and product should have an independent Product Backlog

  3. C

    There are multiple product features being developed by the same team.

  4. D

    There are multiple teams working on the components of the same product. Each team should an independent Product Backlog

Show answer and explanation

Correct answer: B

Question 3 Single choice

True or False: The Scrum Framework encompasses rules or guidelines for architecture?

  1. A

    True

  2. B

    False

Show answer and explanation

Correct answer: B

Question 4 Single choice

As the Sprint planning progresses, the workload has grown beyond the development team's capacity.

Which action makes most sense for the Team?

  1. A

    Work overtime for the Sprint

  2. B

    Collaborate with the Product Owner and potentially remove or change items

  3. C

    Cancel the Sprint

  4. D

    Star the Sprint and recruit additional team members

Show answer and explanation

Correct answer: B

Question 5 Single choice

Who should know the most about the progress toward a business objective or a release, and be able to explain the alternatives most clearly?

  1. A

    The Product Owner

  2. B

    The Scrum Master

  3. C

    The Project Manager

  4. D

    The Development Team

Show answer and explanation

Correct answer: A

Question 6 Single choice

_____________ can change the priority of items in the _________ backlog at any time.

  1. A

    The Team; Product

  2. B

    The Product Owner(s); Sprint

  3. C

    The Product Owner(s); Product

  4. D

    The Scrum Master; Sprint

Show answer and explanation

Correct answer: C

Question 7 Single choice

Who is required to attend the Daily Scrum?

  1. A

    Scrum Master

  2. B

    Development Team

  3. C

    Development Team and Product Owner

  4. D

    Development Team and Scrum Master

Show answer and explanation

Correct answer: B

Question 8 Single choice

Who defines the Sprint Backlog scope?

  1. A

    Product Owner

  2. B

    Development Team

  3. C

    Scrum Master

  4. D

    Stakeholders

Show answer and explanation

Correct answer: B

Question 9 Single choice

Who has the authority to cancel a Sprint?

  1. A

    The team members

  2. B

    The Scrum Master

  3. C

    The Product Owner

  4. D

    The Project Manager

Show answer and explanation

Correct answer: C

Question 10 Single choice

How should items in the Product Backlog be ordered?

  1. A

    Alphabetically first and then by list order in the Product Backlog

  2. B

    Grouped by business features first and then chronologically by date of original business request

  3. C

    Prioritized by business importance first. The items that result in biggest ROI, must be priorized first

  4. D

    Chronologically by date of original business request first and then by list order in the Product Backlog

Show answer and explanation

Correct answer: C