The primary outcome of frequent replenishments in a distribution requirements planning (DRP) system is that:
A. lead times to customers decrease.
B. transportation costs decrease.
C. the level of required safety stock is reduced.
D. more efficient load consolidation occurs.
Information regarding a major new customer is received from sales. The company's most appropriate initial response would be to adjust the:
A. production volume.
B. master production schedule (MPS).
C. sales and operations plan.
D. forecast.
Increased use of third-party logistics (3PL) services is likely to have which of the following effects on a firm's balance sheet?
A. Decreased fixed assets
B. Decreased retained earnings
C. Increased accounts receivable
D. Increased intangible assets
A company has a demand for 30 units of A, 40 units of B, and 50 units of C. These products are scheduled to run daily in batches of 10 as follows: ABC, ABC, ABC, CBC. What is this scheduling
technique called?
A. Mixed-model
B. Matrix
C. Synchronized
D. Line balancing
Which of the following items does the master scheduler have the authority to change in the master scheduling process?
A. Product mix
B. Aggregate volume
C. Engineering change effectivity date
D. Customer order quantities
We have observed the inventory system does not handle plastic parts well." What should be added to the problem statement to make it more useful?
A. Measurements that help describe the problem
B. Guidance to which problem-solving tools should be used
C. Criteria for selecting the improvement team
D. Description of who is responsible for the problem
An example of an assignable cause of variation in process performance is:
A. power fluctuation during machine operation.
B. machine vibration during operation.
C. incorrect setup of a machine by the operator.
D. changes in temperature in the machine shop.
Which of the following conditions is most likely to result in planned production that is greater than the total demand over the sales and operations planning (SandOP) horizon for a product family that is made to stock?
A. An increase in the customer service level is planned for the product family.
B. New models are being added to the product family.
C. Planned ending inventory for the product family is less than the beginning inventory.
D. There is a long-term upward trend in demand for the product family.
A company's primary performance objective Is flexibility. Which of the following measurements is most important?
A. Labor productivity
B. Schedule adherence
C. Machine changeover time
D. Cycle time
Improvements in an Input/output control (I/O control) system will most likely lead to:
A. flattened bills of material (BOMs).
B. a change in operation sequencing.
C. reduction in queue size and queue time.
D. fewer engineering change notifications.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.