CPIM Exam Details

  • Exam Code
    :CPIM
  • Exam Name
    :Certified in Planning and Inventory Management (CPIM 8.0)
  • Certification
    :APICS Certifications
  • Vendor
    :APICS
  • Total Questions
    :225 Q&As
  • Last Updated
    :May 25, 2026

APICS CPIM Online Questions & Answers

  • Question 121:

    Preventive maintenance plus continuing efforts to adapt, modify, and refine equipment to increase flexibility, reduce material handling, and promote continuous flow, is called:

    A. Source maintenance
    B. Pull-up system
    C. Total productive maintenance
    D. valid schedule maintenance

  • Question 122:

    A company's primary performance objective Is flexibility. Which of the following measurements is most important?

    A. Labor productivity
    B. Schedule adherence
    C. Machine changeover time
    D. Cycle time

  • Question 123:

    In which of the following phases of the product life cycle is product price most effective in influencing demand?

    A. Introduction
    B. Growth
    C. Maturity
    D. Decline

  • Question 124:

    The formula to calculate the Mean Absolute Deviation (MAD) is:

    A. MAD = (sum of mean deviations / number of facts)
    B. MAD = (sum of absolute deviations / number of observations)
    C. MAD = (sum of random deviations / number of average observations)
    D. MAD = (sum of absolute deviations / number of average forecasts)

  • Question 125:

    What is the total load requirement for this work center based on the following data?

    A. 1.326
    B. 1.525
    C. 1,533
    D. 2,880

  • Question 126:

    MRP and CRP should form part of a/an?

    A. Open system
    B. Closed-loop system
    C. Balanced system
    D. Workable plan that meets the priority objectives

  • Question 127:

    Which four primary plant types are defined, and they are used to specify the flow of materials through a production process?

    A. I-plant, A-plant, B-plant, G-Plant
    B. I-plant, A-plant, V-plant, T-Plant
    C. C-plant, K-plant, B-plant, S-Plant
    D. A-plant, D-plant, B-plant, F-Plant

  • Question 128:

    A company assembles kits of hand tools after receipt of the order from distributors and uses two-level master scheduling. The appropriate levels of detail for the forecasts that are input to master scheduling would be total number of kits and:

    A. each unique tool.
    B. percentage of total for each tool.
    C. raw material requirements.
    D. specific kit configurations.

  • Question 129:

    demand or lead time. is held to cover random unpredictable variations in supply and

    A. Safety stock
    B. Variant stock
    C. Anticipatory change inventory
    D. Random contemporary stock

  • Question 130:

    Typically, rough-cut capacity planning (RCCP) in a job shop environment would review which of the following work centers to determine the ability to execute the plan?

    A. Critical work centers only
    B. Gateway work centers only
    C. Final assembly work centers only
    D. All work centers

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.