It takes an average of 3 hours to set up a model and 1 hour to run, but depending on the complexity of the models, the setup time can be significantly different. Last week. 2 modelers were working on different projects. Each worked 40 hours.
One modeler finished 5 models a day, and the other finished 1 model a day.
What was the demonstrated capacity last week?
A. 25models
B. 15models
C. 10models
D. 30models
An example of a cradle-to-cradle sustainability model would be:
A. a laundry service collects dirty baby clothes from families; cleans the clothes in large, efficient batches; and then sorts and delivers the clothes back to each family.
B. a coffee shop collects paper waste in its restaurants, has a selected supplier collect the paper waste to be recycled, and then purchases paper products from that supplier.
C. a company uses wood that has been gathered from multiple sources to construct items, such as beds and toys for babies and young children.
D. a bank offers the lowest interest rates on loans to firms that are committed to using recycled materials and implementing zero-waste initiatives in their processes.
A company is having trouble with raw material deliveries and has decided to develop a supplier certification program. The certification process most appropriately would start with which of the following suppliers?
A. Suppliers of "A" classified items
B. Suppliers recently ISO 9000 certified
C. Suppliers with the worst performance records
D. Suppliers with vendor-managed inventory (VMI)
Substituting capital equipment in place of direct labor can be economically Justified for which of the following scenarios?
A. Volumes are forecasted to increase
B. Material prices are forecasted to increase
C. Implementing a pull system in production
D. Functional layouts are being utilized
The primary reason for tracing a component with scheduling problems to Its master production schedule (MPS) item is to:
A. revise the rough-cut capacity plan.
B. reschedule a related component on the shop floor.
C. check the accuracy of the bills for the MPS items.
D. determine if a customer order will be impacted.
For a company that uses first in, first out (FIFO) inventory accounting, the actual use in production of a recently arrived shipment of more expensive components rather than lower-cost components
previously received will have which of the following results?
A. Higher cost of goods sold (COGS)
B. Lower COGS
C. No change to COGS
D. A violation of FIFO rules
Global outsourcing and shared suppliers serving an industry are drivers of which category of risk?
A. Supply disruptions
B. Forecast inaccuracy
C. Procurement problems
D. Loss of intellectual property
Which of the following outcomes Is a benefit of mixed-model scheduling?
A. Increased inventory
B. Improved demand response
C. Fewer setups
D. Fewer material shortages
Typically, rough-cut capacity planning (RCCP) in a job shop environment would review which of the following work centers to determine the ability to execute the plan?
A. Critical work centers only
B. Gateway work centers only
C. Final assembly work centers only
D. All work centers
An order winner during the growth stage of a product's life cycle is:
A. variety.
B. availability.
C. dependability.
D. price.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.