APICS APICS Certifications CPIM-MPR Questions & Answers

  • Question 41:

    The process of determining in detail the amount of labor and machine resources needed to achieve the required production id known as: A. Resource Plan

    B. Material Requirement Plan

    C. Capacity Requirements Plan

    D. Production Plan

  • Question 42:

    What are usually stated in units of product or some standard unit of output?

    A. Priority plans

    B. Capacity available

    C. Capacity plans

    D. None of the above

  • Question 43:

    To check the feasibility of the master Production Planning, provide warnings to any bottlenecks; ensure utilization of work centers and advice vendors of capacity requirements is the purpose of:

    A. Realistic capacity planning

    B. Expected capacity planning

    C. Rough-cut capacity planning

    D. Work-capacity planning

  • Question 44:

    What involves long-range capacity resource requirements and is directly linked to production planning?

    A. Resource acquisition

    B. Resource planning

    C. Resource capacity

    D. Resource schedule

  • Question 45:

    The amount of released and planned work assigned to a facility for a particular time period is called:

    A. Assignment

    B. Load

    C. Agility

    D. Management

  • Question 46:

    Who is responsible for determining the capacity needed to achieve the priority plans as well as providing, monitoring, and controlling that capacity so the priority plan can be met?

    A. Capacity Running

    B. Capacity Board

    C. Capacity Organization

    D. Capacity Management

  • Question 47:

    The process of monitoring production output, comparing it with capacity plans and taking corrective action when needed is known as:

    A. Capacity Manipulation

    B. Capacity Inspection

    C. Capacity Control

    D. Capacity Management

  • Question 48:

    What is the capacity of a system or resource to produce a quantity of output in a given time period?

    A. Capacity available

    B. Capacity required

    C. Capacity check

    D. Capacity on hand

  • Question 49:

    Capacity is the quantity of work done and not the rate of doing work.

    A. True

    B. False

  • Question 50:

    is the amount of work that can be done in a specified time period.

    A. Size

    B. Role

    C. Capacity

    D. Scope

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM-MPR exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.