Which demand category would a demand manager select, if they need to create an enhancement?
A. Change
B. Strategic
C. Defect
D. Operational
The color band at the top of the project card in Project Workspace displays what project attribute?
A. Issues
B. Risk
C. Status
D. State
The Defect and Enhancement type choices on a demand form are available only when which plugin is installed?
A. Agile Development 2.0
B. Ideation with PPM
C. Test Management 2.0
D. Investment Funding for PPM
Idea [im_idea_core] is directly extended from which table?
A. Project
B. It is not extended from any table.
C. Idea Modules
D. Task
Expenses and costs for a particular demand should be estimated before screening. When preparing the financials of a demand, what determines the present value of future cash flows?
A. Financial Return.
B. Planned ROI.
C. Internal Rate of Return %.
D. Discount Rate %.
If the `Move project for WIP projects' property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states? (Choose two.)
A. Pending
B. Closed
C. Work in Progress
D. Open
Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
A. `Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'.
B. `Enable altering of planned date for task in WIP/Closed'.
C. `Rollup project start date from tasks'.
D. `Calculate ROI percentage based on a project's estimated cost and its net value'.
If a project manager is responsible for approving time sheets or submitting time cards on behalf of team members, they should be given what role?
A. form_admin.
B. approval_admin.
C. timecard_admin.
D. activity_admin.
Which of the following can be used to calculate planned cost when creating a resource plan? (Choose two.)
A. Default rate
B. Rate card
C. Demand rate
D. Project rate
A user's availability is calculated as:
A. Allocated time
B. Capacity minus allocation
C. Allocated hours divided by the total capacity
D. Sum of allocated and confirmed hours, divided by the total capacity
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ServiceNow exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CIS-PPM exam preparations and ServiceNow certification application, do not hesitate to visit our Vcedump.com to find your solutions here.