  • Question 41:

    All of the following are inputs to project schedule development EXCEPT:All of the following are inputs to project schedule development EXCEPT:

    A. change requests
    B. lead- and lag-times.
    C. resource requirements.
    D. resource availability.

  • Question 42:

    Certkiller scans 500 8,5" x 11" two-page, duplex documents every day as 300 dpi Group 4 TIFF images. If each imaged page is an average of 50KB, approximately how many days can they operate before they run out of storage space on their 60GB hard drive?

    A. 300 days
    B. 600 days
    C. 950 days
    D. 1,200 days

  • Question 43:

    Documents were processed by the Document Management System (DMS), originated from a word processor and printed to an image driver as TIFF Group 4 images. These images will be added into the DMS and need to be full text searchable. Which technology will help accomplish this?

    A. Magnetic Ink Character Recognition (MICR)
    B. ICR
    C. OCR
    D. Duplexing

  • Question 44:

    If a group of users has difficulty accessing backfile documents on a near-line device, then which of the following devices would most likely be the cause?

    A. Jukebox
    B. RAID Unit
    C. Image Server
    D. Application Server

  • Question 45:

    A company has requested a system to capture faxes for storage after they arrive and are printed. An alternate scalable solution would include a(n):

    A. high speed document scanner.
    B. e-mail server capture solution.
    C. fax server capture solution.
    D. Internet fax solution.

  • Question 46:

    While reviewing a projects proposed timeline, it is found that the Document Management System (DMS) rollout schedule is unrealistic. A discussion should be held FIRST with the:

    A. Chief Executive Officer (CEO).
    B. project sponsor.
    C. end-users.
    D. system storage managers.

  • Question 47:

    When a disaster recover plan is designed, a company should do which of the following?

    A. Hire a records manager.
    B. Move all of the records off site.
    C. Consider the cost implementation.
    D. Identify the vital records within the organization.

  • Question 48:

    The BEST solution for indexing hand printed notes is:

    A. OCR.
    B. ICR.
    C. Optical Mark Recognition (OMR).
    D. Magnetic Ink Character Recognition (MICR).

  • Question 49:

    One of the largest obstacles when implementing a Document Imaging System (DIS) is:

    A. labor cost.
    B. resistance to change.
    C. difficulty of use
    D. high cost of storage.

  • Question 50:

    Certkiller processes a very large number of invoices daily that are of non-standard sized and different thickness. Which of the following is the most important criterion for selecting a scanner for Certkiller ?

    A. ADF
    B. Lamps
    C. High Speed
    D. Despeckling

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CD0-001 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.