  • Question 81:

    When does the lessons learned document is updated?

    A. At planning phase.
    B. At execution phase.
    C. At closing phase.
    D. Throughout the project lifecycle.

  • Question 82:

    A conservative company with rigorous risk control plans and internal audit rules has a recurrent problem with a core business application. As a result, access to this application must be restricted and controlled and maintenance must be on-site. However, the company feels that the application must have an emergency service team. The routine maintenance of this solution is provided by an external vendor and the vendor requested 24 hours remote access to quality and production data. In this context, what is the company's response to the vendor's request?

    A. Denied, because the vendor requested it
    B. Denied, because of the company's risk aversion
    C. Accepted, because the company has an urgent problem to solve
    D. Accepted, because immediate remote access will resolve any issue

  • Question 83:

    The ____, an output of the define scope process, does document the process and criteria for accepting completed products.

    A. Statement of Work
    B. Contract
    C. Project scope statement
    D. Project management plan

  • Question 84:

    Henry is the business analyst for his organization and is completing the conduct elicitation activity. Part of this activity is to record the results of the requirements elicitation process.

    All of the following are acceptable elements for requirements documentation except for which one?

    A. Text message sent via a secured mobile phone
    B. Written documents describing the outcomes
    C. Visual or audio recordings
    D. Whiteboards

  • Question 85:

    As part of identifying an enterprise's capability to adopt a potential solution, a business analyst (BA) is reviewing existing processes and tools within the enterprise for their ability to adapt to a new solution.

    Which of the following assessments is the BA performing?

    A. Stakeholder
    B. Enterprise
    C. Organizational
    D. Operational

  • Question 86:

    A large health care provider has recently purchased and installed a solution that automates some of the activities that coordinate patient recovery activities. A business analyst (BA) is in the process of evaluating this solution and analyzing the performance measures against the value it brings. At this juncture, the BA has uncovered some threats in the solution which could hamper its performance and erode the value it brings.

    Which technique will enable the BA to record and handle these on an ongoing basis?

    A. Risk Analysis and Management
    B. Root Cause Analysis
    C. Solution Performance Analysis
    D. Solution Scope

  • Question 87:

    The requirements elicitation process requires that the business analyst and team prepare for the requirements elicitation activities. There are three specific inputs that the business analyst will need in preparing for the requirements elicitation. Which of the following is NOT one of the three inputs the business analyst will use as he prepares for requirements elicitation?

    A. Solution scope
    B. Change request
    C. Business need
    D. Stakeholder list

  • Question 88:

    During a prioritization meeting, a business analyst (BA) mentioned that the access management system requirements are not stable. The project manager and a team lead proposed removing the requirements from discussion. A domain subject matter expert (SME) insisted on making that requirement a high priority, because it is really important from their point of view.

    What should the BA do?

    A. Make the requirement a lower priority to minimize unanticipated rework and wasted effort
    B. Set the requirements at a high priority to adhere to the SME's point of view
    C. Remove the requirement from the project
    D. Leave priority unfilled for these requirements

  • Question 89:

    Which one of the following statements best describes requirements prioritization?

    A. It determines how requirements will be prioritized based on the most important stakeholders to the least important stakeholders.
    B. It is only used with the change-driven approach to business analysis.
    C. It is only used with the plan-driven approach to business analysis.
    D. It determines how requirements will be prioritized and how those priorities will be used to define the solution scope.

  • Question 90:

    Which of the following are directed conversations for gathering ideas, opinions about a product, service, problem, or opportunity?

    A. Interviews
    B. Group discussions
    C. Feedback loops
    D. Focus groups

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IIBA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CBAP exam preparations and IIBA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.