  • Question 951:

    The Identify Stakeholders process is found in which Process Group?

    A. Initiating
    B. Monitoring and Controlling
    C. Planning
    D. Executing

  • Question 952:

    Specification of both the deliverables and the processes is the focus of:

    A. Change control
    B. Configuration control
    C. Project monitoring and control
    D. Issue control

  • Question 953:

    DRAG DROP

    Drag the five stages of team development on the left onto the blocks on the right to place them in sequential order.

    Select and Place:

  • Question 954:

    A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity.

    How can the project manager assist the team to resolve the issue?

    A. Request the new resource be relocated with the rest of the team and document a change request for the project.
    B. Ask the team to identify possible options to resolve the issue with minimal impact to the new resource.
    C. Log this issue in the issue log and escalate it to the management team, asking them to replace the new team member.
    D. Consult the communications management plan to review available options, such as special virtual meetings, with the new resource.

  • Question 955:

    Which of the following are outputs of Develop Project Team?

    A. Human resources plan changes and project staff assignment updates
    B. Project management plan updates and enterprise environmental factor updates
    C. Resource calendars and project management plan updates
    D. Team performance assessments and enterprise environmental factor updates

  • Question 956:

    A construction project team has just had an inevitable delay due to a natural calamity. What should the project manager do next?

    A. Use expert judgment
    B. Use organizational process assets
    C. Consult the project management plan
    D. Consult the risk register

  • Question 957:

    Which of the following is the primary output of the Identify Risks process?

    A. Risk management plan
    B. Risk register
    C. Change requests
    D. Risk response plan

  • Question 958:

    What major skill sets comprise the PMI Talent Triangle?

    A. Technical project management, technology management, and strategic and business management
    B. Technical project management, leadership, and strategic and business management
    C. Leadership, operational management, and technical project management
    D. Organizational management, operational management, and technology management

  • Question 959:

    Which item is a cost of conformance?

    A. Training
    B. Liabilities
    C. Lost business
    D. Scrap

  • Question 960:

    Which process numerically analyzes the effect of identified risks on overall project objectives?

    A. Plan Risk Management
    B. Plan Risk Responses
    C. Perform Quantitative Risk Analysis
    D. Perform Qualitative Risk Analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.