PMI CAPM Online Questions & Answers

  • Question 791:

    What tool or technique is primarily used to plan risk responses?

    A. Risk categorization
    B. Project risk document updates
    C. Strategies for overall project risk
    D. Risk management plan

  • Question 792:

    In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

    A. enterprise environmental factors
    B. organizational process assets
    C. project management plan
    D. project funding requirements

  • Question 793:

    A project manager is talking with their manager about the advantages of following a particular project management approach. What component of the project manager's sphere of influence does this represent?

    A. The project
    B. The organization
    C. Professional discipline
    D. Across disciplines

  • Question 794:

    In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

    A. Schedule
    B. Quality
    C. Communications
    D. Cost

  • Question 795:

    Which contract type is least desirable to a vendor?

    A. Fixed price with economic price adjustment (FPEPA)
    B. Firm fixed price (FFP)
    C. Cost plus fixed fee (CPFF)
    D. Cost plus award fee (CPAF)

  • Question 796:

    Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

    A. Cost management plan.
    B. Work performance information.
    C. Quality management plan.
    D. Work breakdown structure.

  • Question 797:

    The precedence diagramming method (PDM) is also known as:

    A. Arrow Diagram.
    B. Critical Path Methodology (CPM).
    C. Activity-On-Node (AON).
    D. schedule network diagram.

  • Question 798:

    An organization is faced with increasing demand from the board of directors. They say budgets are exible as long as the work gets completed.

    What project management approach should the organization use?

    A. Predictive
    B. Iterative
    C. Adaptive
    D. Hybrid

  • Question 799:

    DRAG DROP

    Match each dimension of the communications management plan to its corresponding focus.

    Select and Place:

  • Question 800:

    A procurement management plan is a subsidiary of which other type of plan?

    A. Resource plan
    B. Project management plan
    C. Cost control plan
    D. Expected monetary value plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.