  • Question 811:

    Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

    A. Work breakdown structure
    B. Organizational breakdown structure
    C. Resource breakdown structure
    D. Bill of materials

  • Question 812:

    Recently, the government published a new tax law giving companies one year to implement the changes. A project was initiated to change the accounting system.

    Which delivery approach is most suitable in this context?

    A. Predictive, because the requirements are clearly defined up-front.
    B. Adaptive, because the changes have never been implemented before.
    C. Predictive, because of the high risk that the company can be fined.
    D. Adaptive, because the government will provide constant feedback.

  • Question 813:

    An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

    Which two of the following items should be included in the planning? (Choose two.)

    A. Sprint backlog
    B. Increments
    C. Daily scrum
    D. Sprint retrospective
    E. Sprint review

  • Question 814:

    A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

    A. Elicit product requirements.
    B. Manage the project schedule.
    C. Allocate project resources.
    D. Verify product functionality.

  • Question 815:

    Which task will a project manager undertake while conducting Project Resource Management?

    A. Identify the different aspects of the team to manage and control physical resources efficiently
    B. Procure equipment, materials, facilities, and infrastructure for the project
    C. Train the team members in project skill sets
    D. Define the roles and responsibilities of each team member

  • Question 816:

    An issue log is an input to which Project Human Resource Management process?

    A. Manage Project Team
    B. Acquire Project Team
    C. Plan Human Resource Management
    D. Develop Project Team

  • Question 817:

    Which is an output of the Collect Requirements process?

    A. Requirements traceability matrix
    B. Project scope statement
    C. WBS dictionary
    D. Work performance measurements

  • Question 818:

    Which risk response strategy is common for both positive and negative risks?

    A. Share
    B. Accept
    C. Mitigate
    D. Transfer

  • Question 819:

    The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?

    A. Project charter and stakeholder engagement plan
    B. Risk management plan and stakeholder engagement plan
    C. Communications management plan and stakeholder engagement plan
    D. Project charter and communications management plan

  • Question 820:

    Which is a list of organizational systems that may have an impact on a project?

    A. Internal policies, company procedures, and organizational resources
    B. Company culture, purchasing system, and project management information system
    C. Organizational structure, governance framework, and management elements
    D. Organizational process assets, enterprise environmental factors, and corporate knowledge

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.