  • Question 771:

    The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

    A. Close Procurements.
    B. Control Procurements.
    C. Plan Procurements.
    D. Conduct Procurements.

  • Question 772:

    Lessons learned are created and project resources are released in which Process Group?

    A. Planning
    B. Executing
    C. Closing
    D. Initiating

  • Question 773:

    Which process should be conducted from the project inception through completion?

    A. Monitor and Control Project Work
    B. Perform Quality Control
    C. Perform Integrated Change Control
    D. Monitor and Control Risks

  • Question 774:

    Who is responsible for initiating a project?

    A. Project sponsor
    B. Project manager
    C. Program manager D. Project management office (PMO)

  • Question 775:

    If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst- case duration is 14 weeks, how many weeks is the expected duration of the activity?

    A. One
    B. Five
    C. Six
    D. Seven

  • Question 776:

    A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.

    Which activity is the project team conducting?

    A. Brainstorming
    B. Benchmarking
    C. Project initiation
    D. Project execution

  • Question 777:

    What estimating technique is used when there is limited information?

    A. Analogous estimating
    B. Parametric estimating
    C. Bottom-up estimating
    D. Three-point estimating

  • Question 778:

    What scenario describes when a project must be created due to market demand?

    A. A public company authorizes a project to create a new service for electric car sharing to reduce pollution.
    B. A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.
    C. Researchers develop an autonomous car. with several new features to be commercialized in the future.
    D. Stakeholders request that raw matenais be changed due to locally high costs.

  • Question 779:

    Which Manage Communications tool or technique focuses on identifying and managing barriers?

    A. Communication methods
    B. Information technology
    C. Communication models
    D. Information management systems

  • Question 780:

    Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

    A. Critical path method
    B. Critical chain method
    C. Resource leveling
    D. Schedule network analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.