  • Question 481:

    The purpose of inspection in Perform Quality Control is to keep errors:

    A. in line with a measured degree of conformity.
    B. out of the hands of the customer.
    C. in a specified range of acceptable results.
    D. out of the process.

  • Question 482:

    The scope management plan and scope baseline are contained in:

    A. organizational process assets
    B. a requirements traceability matrix
    C. the project charter
    D. the project management plan

  • Question 483:

    Monte Carlo is which type of risk analysis technique?

    A. Probability
    B. Quantitative
    C. Qualitative
    D. Sensitivity

  • Question 484:

    The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

    A. operate separately.
    B. move together in batches,
    C. overlap and interact.
    D. move in a sequence.

  • Question 485:

    What are the identified risks for doing excessive decomposition in a WBS?

    A. Insufficient project funding and disqualification of sellers
    B. Insufficient project funding and ineffective use of resources
    C. Disqualification of sellers and non-productive management efforts
    D. Non-productive management effort and inefficient use of resources

  • Question 486:

    What is the difference between quality metrics and quality measurements?

    A. Quality metrics are product attributes and the measurement is the result of the Monitor and Control Project process
    B. Quality metrics are the result of the Monitor and Control Project process and the measurements are product attributes
    C. Quality metrics and measurements are the same concept
    D. Quality metrics is the general objective and the measurements are the specific objectives

  • Question 487:

    The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

    A. Develop Project Team.
    B. Manage Project Team.
    C. Acquire Project Team.
    D. Plan Human Resource Management.

  • Question 488:

    DRAG DROP

    Match each tool or technique with an appropriate example of that tool or technique.

    Select and Place:

  • Question 489:

    The cost of nonconformance in a project includes:

    A. testing
    B. rework
    C. inspections
    D. training

  • Question 490:

    Analyzing activity sequences, durations, resource requirements, and schedule constraints for project and monitoring and controlling relates to which process?

    A. Develop Schedule
    B. Control Schedule
    C. Estimate Activity Durations
    D. Define Activities

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.