  • Question 391:

    What tool or technique uses an algorithm or statistical relationship between historical data and other variables to calculate an activity's needed resource quantities?

    A. Expert judgment
    B. Bottom-up estimating
    C. Parametric estimating
    D. Analogous estimating

  • Question 392:

    A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process.

    Which responsibility is the most important?

    A. Approving the change
    B. Discussing the change
    C. Reviewing the change
    D. Analyzing the change

  • Question 393:

    Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

    A. Conduct Procurements.
    B. Close Procurements.
    C. Administer Procurements,
    D. Plan Procurements.

  • Question 394:

    Which process is engaged when a proiect learn inember makes a change to project budget with the project manager's approval?

    A. Manage Cost Plan
    B. Estimate Costs
    C. Determine Budget
    D. Control Costs

  • Question 395:

    When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?

    A. Upper and lower control limits
    B. Upper and lower specification limits
    C. Process mean
    D. Data points

  • Question 396:

    What should a project manager reference to understand where responsibility, accountability, and authority reside within a company?

    A. Project charter
    B. Scope of work
    C. Project management system
    D. Organizational system

  • Question 397:

    What is the term assigned to products or services having the same functional use but different technical characteristics?

    A. Scope
    B. Quality
    C. Specification
    D. Grade

  • Question 398:

    Which type of dependency is contractually required or inherent in the nature of the work?

    A. External
    B. Lead
    C. Discretionary
    D. Mandatory

  • Question 399:

    Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

    A. Supportive
    B. Directive
    C. Controlling
    D. Instructive

  • Question 400:

    A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

    Which of the following project delivery approaches should be recommended?

    A. Adaptive
    B. Traditional
    C. Extreme
    D. Hybrid

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.