PMI CAPM Online Questions & Answers

  • Question 331:

    What is the name of a graphic display of project team members and their reporting relationships?

    A. Role dependencies chart
    B. Reporting flow diagram
    C. Project organization chart
    D. Project team structure diagram

  • Question 332:

    Which of the following is a tool or technique used in the Determine Budget process?

    A. Variance analysis
    B. Three-point estimating
    C. Bottom-up estimating
    D. Historical relationships

  • Question 333:

    Which is one of the major outputs of Sequence Activities?

    A. Responsibility assignment matrix (RAM)
    B. Work breakdown structure (WBS) update
    C. Project schedule network diagram
    D. Mandatory dependencies list

  • Question 334:

    Which of the following is a tool and technique used in the Develop Schedule process?

    A. Three-point estimates
    B. Resource leveling
    C. Precedence diagramming method
    D. Bottom-up estimating

  • Question 335:

    A graphic display of project team members and their reporting relationships is known as a:

    A. Resource calendar.
    B. Project organization chart.
    C. Resource breakdown structure (RBS).
    D. Responsibility assignment matrix (RAM).

  • Question 336:

    What are the project management processes associated with project quality management?

    A. Plan Quality Management, Manage Quality, and Control Quality
    B. Plan Quality Management, Manage Quality, and Cost of Quality
    C. Manage Quality, Customer Satisfaction, and Control Quality
    D. Customer Satisfaction, Control Quality, and Continuous Improvement

  • Question 337:

    Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results?

    A. Procurement management plan
    B. Procurement statement of work
    C. Request for proposal
    D. Request for quote

  • Question 338:

    The following is a network diagram for a project.

    The free float for Activity H is how many days?

    A. 4
    B. 5
    C. 10
    D. 11

  • Question 339:

    The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

    A. exploit
    B. avoid
    C. mitigate
    D. share

  • Question 340:

    Which statement is true about the project management body of knowledge?

    A. Recognized by every project manager
    B. Constantly evolving
    C. The sum of all knowledge related to project management
    D. A sum of knowledge that should be applied on every project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.