  • Question 321:

    A risk that arises as a direct result of implementing a risk response is called a:

    A. contingent risk
    B. residual risk
    C. potential risk
    D. secondary risk

  • Question 322:

    Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

    A. Resource breakdown structure
    B. Physical resources assignment
    C. Team building activities
    D. Integrated Change Control

  • Question 323:

    All testing on a project has been performed successfully and all acceptance criteria have been met.

    What is the next step?

    A. Deliver the product.
    B. Set up a go/no-go meeting.
    C. Set up a meeting with the sponsor.
    D. Wait for the next sprint.

  • Question 324:

    A collection of projects managed as a group to achieve strategic objectives is referred to as a:

    A. plan
    B. process
    C. program
    D. portfolio

  • Question 325:

    A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

    A. Engage customer earlier
    B. Conduct quality audits
    C. Validate Scope
    D. Validate quality requirements

  • Question 326:

    Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

    A. Only once, at the beginning
    B. At the beginning and the end
    C. Once during each phase
    D. Repeatedly

  • Question 327:

    A project manager is creating a project charter to provide a direct link between the project and the organization's strategic objectives. What must be considered when creating this document?

    A. High-level requirements and the project team
    B. Key stakeholder list and contingency reserve
    C. Detailed milestone schedule and project objectives
    D. Project purpose and high-level project description

  • Question 328:

    Which of the following is a schematic display of the project's schedule activities and the logical relationships among them?

    A. Gantt chart
    B. Project schedule network diagram
    C. Project milestone list
    D. Activity list

  • Question 329:

    An input to the Estimate Activity Resources process is:

    A. Activity resource requirements.
    B. Published estimating data.
    C. Resource calendars.
    D. Resource breakdown structure (RBS).

  • Question 330:

    The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

    A. Estimate Costs
    B. Control Costs
    C. Plan Cost Management
    D. Determine Budget

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.