CAPM Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :May 28, 2026

PMI CAPM Online Questions & Answers

  • Question 221:

    Responsible, accountable, consult and inform (RACI) is an example of which of the following?

    A. Text-oriented format
    B. Resource management plan
    C. Organization chart
    D. Responsibility assignment matrix (RAM)

  • Question 222:

    In which project performance domain is the work breakdown structure (WBS) developed?

    A. Delivery performance
    B. Project work
    C. Development approach and life cycle
    D. Planning

  • Question 223:

    Stakeholder identification and engagement should begin during what phrase of the project?

    A. After the project management is completed
    B. After the stakeholder engagement plan is completed
    C. As soon as the project charter has been approved
    D. After the communications management plan is completed

  • Question 224:

    DRAG DROP

    Match each process with its corresponding description.

    Select and Place:

  • Question 225:

    Which are the most important competencies required for a project manager?

    A. Leadership, bilingualism, experience, and technical knowledge
    B. PMP certification, experience, technical knowledge, and post-graduate education
    C. Leadership, strategic and business management, project management knowledge, and technical knowledge
    D. Communication skills, project management knowledge, PMP certification, and availability to travel

  • Question 226:

    DRAG DROP

    Match each tool or technique to its corresponding Project Risk Management process. Click on the tool or technique on the left and drag it to the appropriate gray box in the middle.

    Select and Place:

  • Question 227:

    Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?

    A. Portfolio manager
    B. Project sponsor
    C. Project manager
    D. Project management office

  • Question 228:

    Directing another person to get from one to another using a known set of expected behaviors are the ability to lead a team and inspire them to do their jobs well is related to?

    A. Influence and challenge
    B. Innovation and administration
    C. Leadership and management
    D. Engagement and guidance

  • Question 229:

    While gathering nonfunctional requirements for developing a portal, which three aspects should a business analyst check to ensure that the solution developed will be fit for use by the customer? (Choose three.)

    A. Navigation
    B. Uptime
    C. Data integrity
    D. Ease of use
    E. Reliability

  • Question 230:

    A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

    A. Slack
    B. Float
    C. Lag
    D. Lead

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.