  • Question 131:

    What is an output of the Develop Team process?

    A. Project management information system (PIMS)
    B. Team performance assessments
    C. Resource breakdown structure
    D. Project team assignments

  • Question 132:

    Project managers play a key role in performing integration on a project. What are the three different levels of integration?

    A. Process, cognitive, and context
    B. Complexity, understand, and change
    C. Interact, insight, and leadership
    D. Communication, knowledge, and value

  • Question 133:

    Which tools or techniques will a project manager use for Develop Project Team?

    A. Negotiation
    B. Roles and responsibilities
    C. Recognition and rewards
    D. Prizing and promoting

  • Question 134:

    What type of stakeholder is part of a project manager's sphere of influence on a project?

    A. Customers
    B. Sponsors
    C. Directors
    D. Resource managers

  • Question 135:

    Once the make-or-buy analysis is completed, which document defines the project delivery method?

    A. Procurement statement of work (SOW)
    B. Procurement strategy
    C. Terms of reference
    D. Change request

  • Question 136:

    Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

    A. Cost Plus Incentive Fee (CPIF)
    B. Fixed Price Incentive Fee (FPIF)
    C. Cost Pius Award Fee (CPAF)
    D. Time and Material (TandM)

  • Question 137:

    The process of identifying the stakeholders' information needs is completed during:

    A. Plan Communications.
    B. Manage Stakeholder Expectations.
    C. Stakeholder Analysis.
    D. Identify Stakeholders.

  • Question 138:

    In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

    A. Predictive
    B. Adaptive
    C. A mix
    D. Agile

  • Question 139:

    Which is a tool or technique used in Define Scope?

    A. Templates, forms, and standards
    B. Change requests
    C. Product analysis
    D. Project assumptions

  • Question 140:

    A project manager of a civil construction project is trying to understand the local laws. What example of tailoring procurement could this best be described as?

    A. Compliance and governance
    B. Physical location tailoring
    C. Complexity of procurement
    D. Availability of contractors

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.