  • Question 1321:

    Which of the following is a schedule network analysis technique that takes limited resources into account?

    A. Network reserve analysis
    B. Critical chain method
    C. Lead and lag adjustment
    D. Critical path method

  • Question 1322:

    In Project Resource Management, which process uses recognition and rewards as a tool and technique?

    A. Control Resources
    B. Develop Team
    C. Manage Team
    D. Monitor Team

  • Question 1323:

    What is an input to the stakeholder engagement plan?

    A. Risk register
    B. Project charter
    C. Scope management plan
    D. Schedule management plan

  • Question 1324:

    A project manager who communicates to the project team though email is using which type of communication?

    A. Formal
    B. Informal
    C. Horizontal
    D. Unofficial

  • Question 1325:

    A project manager is performing the procurement management process with three vendors. The project team is reviewing the requests for proposal (RFPs).

    What type of procurement document is the RFP?

    A. Bid document
    B. Statement of work (SOW)
    C. Source selection criteria
    D. Independent cost estimate

  • Question 1326:

    During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

    A. Monitor and Control Project Work
    B. Perform Quality Assurance
    C. Close Project or Phase
    D. Control Scope

  • Question 1327:

    Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?

    A. Increased support and minimized resistance from stakeholders
    B. Increased performance of the project team
    C. Maintenance of stakeholder satisfaction because costs and scope are under control
    D. Updated project documents, as requested by stakeholders

  • Question 1328:

    The Define Scope process is in which of the following Process Groups?

    A. Initiating
    B. Planning
    C. Monitoring and Controlling
    D. Executing

  • Question 1329:

    Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?

    A. Planning and risk management skills
    B. Communication and time management skills
    C. Business intelligence and leadership skills
    D. Strategic and business management skills

  • Question 1330:

    Which role does the project manager resemble best?

    A. Orchestra conductor
    B. Facilities supervisor
    C. Functional manager
    D. School principal

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.