  • Question 1261:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the schedule variance (SV) for Task 8?

    A. -2,000
    B. -1,000
    C. 1,000
    D. 2,000

  • Question 1262:

    Plan Risk Management is the process of defining how to:

    A. Communicate identified risks to the project stakeholders.
    B. Conduct risk management activities for a project.
    C. Analyze the impact a specific risk may have on the project.
    D. Address unexpected risks that may occur during a project.

  • Question 1263:

    Which of the following is an information gathering technique in Identify Risks?

    A. Influence diagrams
    B. Brainstorming
    C. Assumption analysis
    D. SWOT analysis

  • Question 1264:

    Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?

    A. Risk analysis
    B. Risk tolerance
    C. Risk management
    D. Risk attitude

  • Question 1265:

    What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

    A. 0.45
    B. 0.56
    C. 0.70
    D. 1.36

  • Question 1266:

    The primary purpose of the stakeholder register is to:

    A. Record stakeholder issues on the project
    B. Maintain lessons learned earlier in the project
    C. Maintain a list of all project stakeholders
    D. Document change requests and their status

  • Question 1267:

    Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

    A. Video conferencing
    B. Audio conferencing
    C. Shared portal
    D. Email/chat

  • Question 1268:

    The Perform Integrated Change Control process occurs in which Process Group?

    A. Initiating
    B. Executing
    C. Monitoring and Controlling
    D. Planning

  • Question 1269:

    What is both an input and output of the Control Quality process and is updated as a result of this process?

    A. Lessons learned register
    B. Risk register
    C. Enterprise environmental factors (EEFs)
    D. Root cause analysis

  • Question 1270:

    Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

    A. Expert judgment
    B. Forecasting methods
    C. Earned value management
    D. Analytical techniques

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.