PMI CAPM Online Questions & Answers

  • Question 1251:

    What is the number of stakeholders, if the project has 28 potential communication channels?

    A. 7
    B. 8
    C. 14
    D. 16

  • Question 1252:

    A project is in its final stages when a competitor releases a similar product. This could make the project redundant.

    What should the project manager do next?

    A. Initiate change control.
    B. Address risk mitigation.
    C. Initiate project closure.
    D. Escalate this to the project sponsor.

  • Question 1253:

    What tool should a project manager use to efficiently manage project resources?

    A. List of project resources
    B. Resource breakdown structure
    C. Resources detailed in the project scope
    D. Resource requirements

  • Question 1254:

    Which set of tools and techniques is useful for estimating activity durations for the project schedule?

    A. Brainstorming, Monte Carlo Simulation, analogous estimation
    B. Three-point estimation, resources leveling, iteration burndown chart
    C. Milestone charts, parametric estimation, schedule baseline
    D. Parametric estimation, three-point estimation, analogous estimation

  • Question 1255:

    Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

    A. Cost-reimbursable contracts
    B. Time and Material contracts (TandM)
    C. Fixed-price contracts
    D. Cost Plus Fixed Fee Contracts (CPFF)

  • Question 1256:

    Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

    A. portfolio
    B. program
    C. selection
    D. sub portfolio

  • Question 1257:

    At which stage of team development do members begin to work together, adjust work habits, and trust each other?

    A. Forming
    B. Storming
    C. Norming
    D. Performing

  • Question 1258:

    A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?

    A. Collective decision making
    B. Multicriteria decision analysis
    C. Mind mapping
    D. Affinity diagram

  • Question 1259:

    Cost baseline is an output of which of the following processes?

    A. Control Costs
    B. Determine Budget
    C. Estimate Costs
    D. Estimate Activity Resources

  • Question 1260:

    What is a tool or technique used in the Control Quality process?

    A. Attribute sampling
    B. Parametric estimating
    C. Statistical sampling
    D. Expert judgment

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.