SAP SAP Certified Application Associate C_IBP_2202 Questions & Answers

  • Question 31:

    Which of the following are the key features of SAP Supply Chain Control Tower? Note: There are 2 correct Answers to this question.

    A. Ability to balance demand and supply and attain financial targets

    B. Ability to create a feasible plan

    C. Ability to use task and case management

    D. Ability to create smart alerts

  • Question 32:

    What options for copying will be available to you? Note: There are 2 correct Answers to this question.

    A. Creation of a partial copy with a new ID along with the time profile and required master data types

    B. Creation of a partial copy with a new ID along with the time profile and all master data objects

    C. Creation of an exact copy with a new ID, with the time profile and master data types shared with the source

    D. Creation of an exact copy with a new ID along with the time profile and master data types

  • Question 33:

    How can you make charts and dashboards private?

    A. Choose only relevant key figures and filters in the Analytics Advanced application.

    B. Enable the relevant settings in the global configuration parameters.

    C. Set restrictions for charts in the Permission filter application.

    D. Enable the relevant settings in the Analytics Advanced and Dashboards Advanced applications.

  • Question 34:

    You are working to realign the data due to a recent warehouse closure. What should you be aware of in regards to configuration of realignment steps? Note: There are 2 correct Answers to this question.

    A. The name of the realignment step should be no longer than 20 characters.

    B. If a realignment step fails, subsequent steps are not processed.

    C. The number of steps in realignment run is limited to 255.

    D. The realignment step status must be set to In Review for it to be executed.

  • Question 35:

    You are adding a value-based filter to a planning view. Which of the following conditions apply? Note: There are 3 correct Answers to this question.

    A. The alerts dashboard is not available if a value-based filter is set for the open planning view.

    B. These filters are always applied based on the values stored in the database.

    C. You can only apply one value-based filter per planning view.

    D. These filters can be used together with attribute totals in the same planning view.

    E. You can add (or delete) planning objects to a planning view after these filters are applied.

  • Question 36:

    SAP is transitioning IBP customers to the new process of export/import. What are some of the features of this new process? Note: There are 2 correct Answers to this question.

    A. You can choose to import only some of the items that were exported.

    B. You can move a transported item from one collection to another.

    C. You can create a collection of items and export it.

    D. You can export from a planning area that is on a different release.

  • Question 37:

    Which of the following modes can you use when creating a constrained plan? Note: There are 2 correct Answers to this question.

    A. Profit maximization

    B. Delivery maximization

    C. Resource maximization

    D. Production maximization

  • Question 38:

    You are creating advanced copy operators as part of an SAP IBP solution that is being implemented.

    What do you need to be aware of when defining data transfer? Note: There are 2 correct Answers to this question.

    A. Specifying target key figure is mandatory.

    B. Specifying target key figure that is time independent is possible.

    C. Specifying source key figure is mandatory.

    D. Selecting by attribute with option 'contain' is possible.

  • Question 39:

    What are some of the prerequisites for configuring a planning area that results in a successful consistency check? Note: There are 2 correct Answers to this question.

    A. Configure at most two input key figures on the same planning level in a key figure calculation.

    B. Assign the compound master data type and its component master data types.

    C. Specify a planning horizon in the planning area for each level of the assigned time profile.

    D. Configure at least one calculated key figure for the planning area.

  • Question 40:

    You are working with the inventory optimization process and you want to use a what-if analysis. What parameters are assessed by this analysis? Note: There are 2 correct Answers to this question.

    A. Changed variability

    B. Service levels

    C. Capacity consumption

    D. Number of planning combinations

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_IBP_2202 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.