IBM IBM Rational C2010-825 Questions & Answers

  • Question 1:

    A developer is working on a task with outgoing change sets in a loaded repository workspace when a manager identifies a new, critical task that must be performed immediately. There are currently no unresolved changes. Without creating another repository workspace, how can the developer safely work on the critical task without losing the pending changes of the initial task?

    A. The user suspends the current change sets and starts working in a new change set.

    B. The user reloads the repository workspace and starts working in a new change set

    C. The user creates a new change set, selects it as the current change set and checks in all changes.

    D. The user loads the repository workspace in a different client and starts working in a new change set.

  • Question 2:

    A project manager asks the administrator to restrict user access to the project area to only people on the

    project.

    Where would the administrator go in order to modify this?

    A. Access Groups

    B. Operational Behaviors

    C. Team Area Permissions

    D. Project Area Access Control

  • Question 3:

    A development has organized the source code into components and found that there is a strong

    dependency or containment relationship between two of the components.

    What action could the development team take to establish this relationship?

    A. Take a baseline of both components.

    B. Update both component's Properties view.

    C. Utilize a work item to link both components.

    D. Create the Child component as a subcomponent of the parent.

  • Question 4:

    What build related activities can a user accomplish using the RTC web client?

    A. Define build scripts

    B. Administer build engines

    C. Request builds and monitor status

    D. Create and modify build definitions

  • Question 5:

    A project has both new development and maintenance work, each with their own schedule. The scrum

    master has organized the project area into development and maintenance team areas. The scrum master

    wants to keep the work effort and planning for both teams separate.

    Which of the below can be defined to facilitate this?

    A. Cross-project plans for both teams.

    B. A timeline and iteration for each team.

    C. Sprint plans that match the team areas and categories.

    D. Divide the release backlog into corresponding team ownership.

  • Question 6:

    A scrum master wants to determine if the team has enough time to complete the work planned for an

    iteration.

    What is used to assess this?

    A. Plan's Task Board View

    B. Ranked List of work items

    C. Load Bar in the Plan Details

    D. Traceability View sorted by Estimate

  • Question 7:

    An administrator is designing the representation of the following: 1) which team is responsible for work items 2) in which build the defects were discovered 3) the timeframe for the work item to be completed

    Which of the following shows the correct relationships?

    A. Categories: Found In Releases: Planned For Iterations: Filed Against

    B. Team Areas: Planned For Releases: Filed Against Iterations: Found In

    C. Categories: Filed Against Releases: Found In Iterations: Planned For

    D. Team Areas: Filed Against Releases: Planned For Iterations: Found In

  • Question 8:

    Which RTC client allows a user to lock and download a source file in a single operation?

    A. Web client

    B. Eclipse client

    C. Explorer Shell

    D. ClearCase bridge

  • Question 9:

    Which build artifact allows developers to associate the outcome with a release?

    A. Build Result

    B. Build Script

    C. Build Engine

    D. Build Definition

  • Question 10:

    A user wants a query to filter work items in the closed group of a workflow. Which option in the query condition allows this?

    A. Resolved

    B. Unassigned

    C. Unresolved

    D. Current Iteration

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IBM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C2010-825 exam preparations and IBM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.