  • Question 141:

    How can the generated forecast dates on a preventive maintenance record be locked in the Preventive Maintenance application?

    A. update the extended date field
    B. change the status to LOCKED
    C. enable the Forecast Dates Locked check box
    D. select Lock Forecast Dates from the Select Action menu

  • Question 142:

    A work order is generated from a route and each stop on the route has a unique job plan and safety plan. Which option should be selected for: When this Route is Applied to a Work Order, the Route Stops will Become?

    A. Child Work Orders
    B. Work Order Tasks
    C. Sequenced Job Plans
    D. Entries in the Work Order's Multi Asset, Location, and CI Table

  • Question 143:

    Job plan's responsibility can be assigned to a supervisor, crew, lead, and owner. Which statement is true regarding a work order that results from a job plan?

    A. The values for supervisor, crew. lead, and owner from the job plan always carry over to the work order regardless of the values for supervisor, crew, lead, and owner defined on the preventive maintenance record.
    B. If the values for supervisor, crew, lead, and owner on the preventive maintenance record are different compared to those on the job plan, the values on the preventive maintenance record take the place of those on the job plan when copied to the work order.
    C. If the values for lead and owner are different on the preventive maintenance record compared to those on the job plan, the values on the preventive maintenance record take the place of those on the job plan when copied to the work order. Values for supervisor and crew come from the job plan.
    D. If the values for lead and owner are different on the preventive maintenance record compared to those on the job plan, the values on the job plan take the place of those on the preventive maintenance record when copied to the work order. Values for supervisor and crew come from the preventive maintenance record.

  • Question 144:

    A customer wants an escalation to automatically close work orders that have been in a complete status for more than 30 days. Which statement is true for this escalation?

    A. The escalation point should be set to repeat.
    B. The escalation point should have an elapsed time interval of 720.
    C. The escalation should have a condition that monitors work order status.
    D. The escalation should have a condition that monitors work order status and change date.

  • Question 145:

    A purchase request line can be added to the purchase requisition through which two methods? (Choose two.)

    A. Vendor Items button
    B. Contract Items button
    C. Select Action > Copy PO Lines
    D. Select Action > Copy RFO Lines
    E. Select Action > Copy Contract Lines

  • Question 146:

    In the Work Order Tracking application, which two actions create a value in the related records table? (Choose two.)

    A. Select Action > Create > Work Order
    B. Select Action > Duplicate Work Order
    C. Select Action > Create Work Package
    D. Select Action > Create > Communication
    E. Select Action > Create > Service Request

  • Question 147:

    A shipment is being received for a rotating item or tool. What is the next step in receiving a rotating tool or item when the status is WINSP?

    A. Assign Asset Number
    B. Receive Rotating Items
    C. Receive Inspected Items
    D. Change Inspection Status for Rotating Items

  • Question 148:

    A reservation is created when a work order is approved with item(s) on the Work Order Plans Materials sub-tab. Which action controls when an item must be specified with a hard reservation?

    A. Change the reservation type on the materials line to HARD
    B. Change the reservation type on the reservation list to HARD
    C. Set the reservation type to HARD within the Organization > Inventory Options
    D. Set the flag on this check box within the Inventory application: Requires hard reservation on use?

  • Question 149:

    Which two items are required to approve a purchase contract? (Choose two.)

    A. A vendor
    B. An authorized site
    C. A total cost greater than zero
    D. At least one contract line item
    E. Association to at least one commodity code

  • Question 150:

    For what purpose is the Activities and Tasks application used?

    A. To plan, review, and manage activities and tasks
    B. To create and manage job plans, activities, and tasks
    C. To plan and manage preventive maintenance, activities, and tasks
    D. To create, plan, and manage preventive maintenance, activities, and tasks

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IBM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C2010-570 exam preparations and IBM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.