  • Question 161:

    What is the initial default status when creating a Request for Quotation?

    A. INPRG
    B. DRAFT
    C. WAPPR
    D. INACTIVE

  • Question 162:

    Safety plans are used on which two IBM Maximo Asset Management V7.5 applications? (Choose two.)

    A. Assets
    B. Job Plans
    C. Work Orders
    D. Service Requests
    E. Preventive Maintenance

  • Question 163:

    What are the three statuses that a shipment receipt record can have when receiving shipment items or tools in the Shipment Receiving application? (Choose three.)

    A. NONE
    B. PARTIAL
    C. RECEIVED
    D. ACCEPTED
    E. COMPLETE
    F. INCOMPLETE

  • Question 164:

    Which statement describes an inventory backorder reservation?

    A. the reservation quantity must be less than 10
    B. the reservation quantity must be greater than 10
    C. the reservation quantity must be satisfied by the current balance on the inventory record
    D. the reservation quantity must be satisfied by the available balance on the inventory record

  • Question 165:

    What is the purpose of the Inventory Usage application?

    A. To list all inventory tool items within a storeroom
    B. To list all inventory service items within a storeroom
    C. To track the issue, transfer, and reuse of inventory items within and across sites
    D. To track the issue, transfer, and return of inventory items within and across organizations

  • Question 166:

    A job plan is used throughout the organization and has six tasks except for one site (site A) that has an additional task. What is the best approach to accomplish this requirement?

    A. Create a job plan with the six tasks that apply to both sites. Create a nested job plan that references the unique task, designate it for site A and associate it with the first task.
    B. For the job plan or tasks, do not define an organization or site. When the work order for a site other than site A is created, delete the task which does not apply from the work order.
    C. For the job plan or the six tasks that apply to both sites, do not define an organization or site. For the additional task that is specific for site A, designate the site ID for that task as site A.
    D. Two job plans are needed: one that is designated as site A at the job plan level and has the seven appropriate job tasks for that site, and one without a defined site for the six job tasks appropriate for the remaining sites.

  • Question 167:

    Which statement describes the function of the Select Items for Return button?

    A. to return excess inventory items to another storeroom bin
    B. to return inventory items to a storeroom found in the workshop
    C. to return issued but unused inventory items to another storeroom
    D. to return issued but unused inventory items to the original storeroom

  • Question 168:

    How are reorder items designated in IBM Maximo Asset Management V7.5?

    A. The item reorder flag is set to Yes in Inventory.
    B. The item reorder flag is set to Yes in the Item Master.
    C. The item stock category is set to Stocked in Inventory.
    D. The item stock category is set to Stocked in the Item Master.

  • Question 169:

    Which statement is true regarding the View Costs table as displayed from the Work Order Tracing application?

    A. The Work Package Totals table shows the cost information for the entire work order hierarchy starting from the current work order.
    B. All actual labor hours are immediately reflected in the View Costs table regardless of the work order or labor transaction approval status.
    C. Service costs include all services acquired on purchase orders that are charged to the work order in addition to all external labor hours managed by valid labor rate contracts.
    D. The data reflected in the Estimate at Approval column reflects the work order costs when first approved and does not change if it is necessary to unapproved the work order to make a change to the estimate.

  • Question 170:

    Where is application access defined?

    A. Rights application
    B. Access application
    C. Security Groups application
    D. Application Definition application

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IBM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C2010-570 exam preparations and IBM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.