  • Question 181:

    A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.

    Before initiating closeout and releasing the resources,

    what should the program manager do?

    A. Review the benefits management plan with the program sponsor
    B. Obtain approval from the sponsor to close the program
    C. Prepare performance evaluations for all program personnel
    D. Prepare performance evaluations for all project personnel

  • Question 182:

    After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

    What should the program manager do next?

    A. Accelerate the projects and components of the program that replace the two legacy systems
    B. Analyze the impact of accelerating the program, and present the pros and cons to the program sponsor
    C. Identify the parts of the program that need to be accelerated and. if it is cost effective and increases benefits realization, implement the change
    D. Create several "what-if" scenarios of alternatives to present to the program sponsor

  • Question 183:

    Which of the following is a wire and cable manufacture's organization that writes telecommunications specifications for the telephone and power cable industries?

    A. IEC
    B. ISO
    C. NFPA
    D. IEEE
    E. ICEA
    F. FCC

  • Question 184:

    An ICT distribution designer is representing a client during a project execution.

    What is the designer's role in the Vendor and Contractor Coordination?

    A. Oversee the sequence of the work and ensure that the job proceeds as anticipated in accordance with the project execution schedule
    B. Synchronizes the daily activities of all trades through daily or weekly meetings (depending on project size, complexity, or criticality) with individual trade PMs. Fore people, supervisors and designers as necessary
    C. Holds two critical meetings to begin the project and allow all parties to introduce themselves. The first meeting usually is conducted with the owner and design team, and the second meeting is with the field personnel and subcontractors
    D. lf specific questions arise regarding coordination of the installation with structural, architectural, and site conditions and work between trades, submit RFIs to the GC with appropriate documentation to demonstrate the concern along with the proposed installation.

  • Question 185:

    Exhibit:

    A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (Americans with Disability Act) requirement for side reach using a wheelchair.

    What will be the maximum reachable height or the value of "X"?

    A. 760 mm (30 in)
    B. 864 mm (34 in)
    C. 1170 mm (46 in)
    D. 1220 mm (48 in)
    E. 1370 mm (54 in)

  • Question 186:

    The CP can be used as a TP for under the carpet cabling.

    A. False
    B. True

  • Question 187:

    Stakeholders make ad-hoc requests on a routine basis.

    This causes duplication of reporting and communication gaps that affect the program's performance To resolve this situation, which of the following must go through critical review and change"?

    A. Program Benefits Management domain
    B. Stakeholder communications requirements
    C. Program communications report
    D. Program communications management plan

  • Question 188:

    To properly size and provide accurate cost estimates for a communications distribution horizontal pathway that will include BAS system infrastructure, the designer should provide ________ for every BAS outlet or device based on total floor area.

    A. 9.30 m2 (100 ft2)
    B. 23.20 m2 (250 ft2)
    C. 91.40 m2 (300 ft2)
    D. 152.40 m2 (500 ft2)

  • Question 189:

    What step can be a phase of the Bidding and Negotiating process?

    A. Prepare necessary change orders
    B. Identifying any conflicts that may become apparent
    C. Creating a response evaluation
    D. Identifying potential value engineering opportunities

  • Question 190:

    A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

    Which of the following deliverables captures these items?

    A. Program scope management plan
    B. Program governance plan
    C. Program scope statement
    D. Program work breakdown structure

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only BICSI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your BICSI-RCDD exam preparations and BICSI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.