GAQM APM-001 Online Questions & Answers

  • Question 81:

    Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

    A. Exploit
    B. Share
    C. Enhance
    D. Transfer

  • Question 82:

    Every project creates a unique product, service, or result that may be:

    A. tangible
    B. targeted
    C. organized
    D. variable

  • Question 83:

    Which stakeholder approves a project's result?

    A. Customer
    B. Sponsor
    C. Seller
    D. Functional manager

  • Question 84:

    Through whom do project managers accomplish work?

    A. Consultants and stakeholders
    B. Stakeholders and functional managers
    C. Project team members and consultants
    D. Project team members and stakeholders

  • Question 85:

    In which process might a project manager use risk reassessment as a tool and technique?

    A. Perform Qualitative Risk Analysis
    B. Monitor and Control Risk
    C. Monitor and Control Project Work
    D. Plan Risk Responses

  • Question 86:

    A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

    A. Projectized
    B. Weak matrix
    C. Functional
    D. Balanced matrix

  • Question 87:

    An input to the Perform Quantitative Risk Analysis process is the:

    A. quality management plan.
    B. project management plan.
    C. communications management plan.
    D. schedule management plan.

  • Question 88:

    Which cost is associated with nonconformance?

    A. Liabilities
    B. Inspections
    C. Training
    D. Equipment

  • Question 89:

    Exhibit A is an example of which of the following types of Sequence Activities?

    A. Activity-on-arrow diagramming
    B. Precedence diagramming
    C. Project schedule network diagramming
    D. Mathematical analysis diagramming

  • Question 90:

    Which type of organizational structure is displayed in the diagram provided?

    A. Balanced matrix
    B. Projectized
    C. Strong matrix
    D. Functional

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.