  • Question 71:

    Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

    A. Requirements documentation
    B. Requirements traceability matrix
    C. Project management plan updates
    D. Project documents updates

  • Question 72:

    A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

    A. Plan Stakeholder Management
    B. Identify Stakeholders
    C. Manage Stakeholder Engagement
    D. Control Stakeholder Engagement

  • Question 73:

    The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

    A. management
    B. response
    C. tolerance
    D. appetite

  • Question 74:

    A project manager builds consensus and overcomes obstacles by employing which communication technique?

    A. Listening
    B. Facilitation
    C. Meeting management
    D. Presentation

  • Question 75:

    Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

    A. Work breakdown structure
    B. Organizational breakdown structure
    C. Resource breakdown structure
    D. Bill of materials

  • Question 76:

    Which of the following is an example of the simplest fixed-price contract?

    A. Purchase requisition
    B. Purchase order
    C. Verbal agreement
    D. Request for quote

  • Question 77:

    Which of the following reduces the probability of potential consequences of project risk events?

    A. Preventive action
    B. Risk management
    C. Corrective action
    D. Defect repair

  • Question 78:

    The Human Resource Management processes are:

    A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
    B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
    C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
    D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

  • Question 79:

    Completion of the product scope is measured against the product:

    A. prototypes
    B. requirements
    C. analyses
    D. benchmarks

  • Question 80:

    At the end of the project, what will be the value of SV?

    A. Positive
    B. Zero
    C. Negative
    D. Greater than one

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.