  • Question 61:

    The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

    A. exploit
    B. avoid
    C. mitigate
    D. share

  • Question 62:

    What is the difference between the critical path and the critical chain?

    A. Scope changes
    B. Resource limitations
    C. Risk analysis
    D. Quality audits

  • Question 63:

    During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

    A. Monitor and Control Project Work
    B. Perform Quality Assurance
    C. Close Project or Phase
    D. Control Scope

  • Question 64:

    Which is one of the determining factors used to calculate CPI?

    A. EV
    B. SPI
    C. PV
    D. ETC

  • Question 65:

    The following is a network diagram for a project.

    The total float for the project is how many days?

    A. 5
    B. 9
    C. 12
    D. 14

  • Question 66:

    Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

    A. Interrelationship digraphs
    B. Tree diagram
    C. Affinity diagram
    D. Network diagram

  • Question 67:

    Which tool or technique is an examination of industry and specific vendor capabilities?

    A. Independent estimates
    B. Market research
    C. Analytical techniques
    D. Bidder conferences

  • Question 68:

    Which of the following is a tool or technique of the Define Activities process?

    A. Rolling wave planning
    B. Precedence diagramming method (PDM)
    C. Alternatives analysis
    D. Parametric estimating

  • Question 69:

    Administer Procurements is part of which Process Group?

    A. Planning
    B. Executing
    C. Monitoring and Controlling
    D. Closing

  • Question 70:

    Which tool is used to develop technical details within the project management plan?

    A. Expert judgment
    B. Project management methodology
    C. Project management information system (PMIS)
    D. Project selection methods

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.