  • Question 51:

    Which of the following is an input to the Perform Qualitative Risk Analysis process?

    A. Risk register
    B. Risk data quality assessment
    C. Risk categorization
    D. Risk urgency

  • Question 52:

    The procurement process that documents agreements and related documentation for future reference is known as:

    A. Plan Procurements.
    B. Control Procurements.
    C. Close Procurements.
    D. Conduct Procurements.

  • Question 53:

    When closing a project or phase, part of the process may require the use of which type of analysis?

    A. Reserve analysis
    B. Regression analysis
    C. Document analysis
    D. Product analysis

  • Question 54:

    Which of the following is a tool and technique used to monitor risk?

    A. Technical performance measurement
    B. Cost performance baseline
    C. Benchmarking
    D. Cost of quality

  • Question 55:

    The formal and informal interaction with others in an organization industry, or professional environment is known as:

    A. negotiation
    B. organizational theory
    C. meeting
    D. networking

  • Question 56:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the cost variance (CV) for Task 6?

    A. -2,000
    C. 1,000
    D. 2,000

  • Question 57:

    An example of a group decision-making technique is:

    A. nominal group technique
    B. majority
    C. affinity diagram
    D. multi-criteria decision analysis

  • Question 58:

    The component of the risk management plan that documents how risk activities will be recorded is called:

    A. tracking
    B. scoping
    C. timing
    D. defining

  • Question 59:

    An input to Develop Project Charter is a/an:

    A. Business case.
    B. Activity list.
    C. Project management plan.
    D. Cost forecast.

  • Question 60:

    Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

    A. Business case
    B. Work breakdown structure
    C. Requirements documentation
    D. Risk register

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.