  • Question 421:

    Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

    A. Reserve analysis
    B. Three-point estimating
    C. Parametric estimating
    D. Analogous estimating

  • Question 422:

    A tool and technique used during the Define Scope process is:

    A. facilitated workshops.
    B. observations.
    C. questionnaires and surveys.
    D. group creativity techniques.

  • Question 423:

    The process of formalizing acceptance of the completed project deliverables is known as:

    A. Validate Scope.
    B. Close Project or Phase.
    C. Control Quality.
    D. Verify Scope.

  • Question 424:

    Which tool or technique is effective in a project in which the deliverable is not a service or result?

    A. Inspection
    B. Variance analysis
    C. Decomposition
    D. Product analysis

  • Question 425:

    A reward can only be effective if it is:

    A. Given immediately after the project is completed.
    B. Something that is tangible.
    C. Formally given during project performance appraisals.
    D. Satisfying a need valued by the individual.

  • Question 426:

    Progressively elaborating high-level information into detailed plans is performed by the:

    A. project management office
    B. portfolio manager
    C. program manager
    D. project manager

  • Question 427:

    The process for performing variance analysis may vary, depending on:

    A. scenario building, technology forecasting, and forecast by analogy.
    B. working relationships among various stakeholders and team members.
    C. application area, the standard used, and the industry.
    D. work to be completed next.

  • Question 428:

    Which of the following is an example of schedule compression?

    A. Activity sequencing
    B. Resource leveling
    C. Lead and lag adjusting
    D. Crashing

  • Question 429:

    A tool and technique used in the Develop Project Charter process is:

    A. change control tools
    B. expert judgment
    C. meetings
    D. analytical techniques

  • Question 430:

    The purpose of inspection in Perform Quality Control is to keep errors:

    A. in line with a measured degree of conformity.
    B. out of the hands of the customer.
    C. in a specified range of acceptable results.
    D. out of the process.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.