  • Question 441:

    Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

    A. Collect Requirements
    B. Direct and Manage Project Execution
    C. Monitor and Control Project Work
    D. Develop Project Management Plan

  • Question 442:

    Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

    A. Corrective action
    B. Defect repair
    C. Preventative action
    D. Probable action

  • Question 443:

    Which provides the basic framework for managing a project?

    A. Project life cycle
    B. Work breakdown structure (WBS)
    C. Enterprise environmental factors
    D. Project initiation

  • Question 444:

    Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

    A. Nominal group technique
    B. Idea/mind mapping
    C. Affinity diagram
    D. Brainstorming

  • Question 445:

    Which of the following processes are part of the Project Integration Management Knowledge Area?

    A. Develop Project Management Plan, Collect Requirements, Create WBS
    B. Develop Project Management Plan, Control Scope, Develop Schedule
    C. Develop Project Charter, Define Scope, Estimate Costs
    D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

  • Question 446:

    A required input for Create WBS is a project:

    A. quality plan.
    B. schedule network.
    C. management document update.
    D. scope statement.

  • Question 447:

    Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

    A. Schedule network analysis
    B. Reserve analysis
    C. Alternative analysis
    D. Variance analysis

  • Question 448:

    An output of the Direct and Manage Project Work process is:

    A. Deliverables.
    B. Activity lists.
    C. A work breakdown structure.
    D. A scope statement.

  • Question 449:

    When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

    A. event.
    B. response.
    C. perception.
    D. impact.

  • Question 450:

    The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

    A. US$158,700
    B. US$172,500
    C. US$187,500
    D. US$245,600

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.