  • Question 281:

    Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

    A. Portfolio
    B. Process
    C. Project
    D. Program

  • Question 282:

    While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

    A. Communications management plan
    B. Human resource plan
    C. Quality management plan
    D. Procurement management plan

  • Question 283:

    Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

    A. Procurement documents
    B. Inspection and audits
    C. Estimate budget
    D. Risk register

  • Question 284:

    The business needs, assumptions, and constraints and the understanding of the customers' needs and high-level requirements are documented in the:

    A. Project management plan.
    B. Project charter.
    C. Work breakdown structure.
    D. Stakeholder register.

  • Question 285:

    Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

    A. Product
    B. Cost-benefit
    C. Stakeholder
    D. Research

  • Question 286:

    The total of the planned value (PV) is also known as:

    A. work breakdown structure (WBS).
    B. schedule target.
    C. performance measurement baseline (PMB).
    D. earned value baseline.

  • Question 287:

    Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

    A. organizational skills
    B. technical skills
    C. communication skills
    D. hard skills

  • Question 288:

    Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

    A. Define Activities
    B. Direct and Manage Project Work
    C. Develop Project Management Plan
    D. Develop Project Charter

  • Question 289:

    The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

    A. Cost Plus Incentive Fee Contract (CPIF).
    B. Cost Plus Fixed Fee Contract (CPFF).
    C. Fixed Price Incentive Fee Contract (FPIF).
    D. Time and Material Contract (TandM).

  • Question 290:

    Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

    A. Scope baseline
    B. Scope management plan
    C. Change management plan
    D. Cost baseline

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.