GAQM APM-001 Online Questions & Answers

  • Question 271:

    Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

    A. Cause and effect diagram
    B. Control charts
    C. Pareto chart
    D. Histogram

  • Question 272:

    Funding limit reconciliation is a tool and technique of which Project Cost Management process?

    A. Estimate Costs
    B. Control Costs
    C. Plan Cost Management
    D. Determine Budget

  • Question 273:

    Which of the following includes how requirements activities will be planned, tracked, and reported?

    A. Configuration management plan
    B. Scope baseline
    C. Requirements management plan
    D. Schedule baseline

  • Question 274:

    Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

    A. Force/direct
    B. Withdraw/avoid
    C. Compromise/reconcile
    D. Collaborate/problem solve

  • Question 275:

    Which activity is an input to the Conduct Procurements process?

    A. Organizational process assets
    B. Resource availability
    C. Perform Integrated Change Control
    D. Team performance assessment

  • Question 276:

    What is a hierarchically organized depiction of the identified project risks arranged by risk category?

    A. Risk register
    B. Risk breakdown structure (RBS)
    C. Risk management plan
    D. Risk category

  • Question 277:

    Projects are undertaken by an organization to support the:

    A. Product performance.
    B. Budget process.
    C. Collective capabilities.
    D. Organizational strategy.

  • Question 278:

    What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

    A. 0.50
    B. 0.67
    C. 1.50
    D. 2.00

  • Question 279:

    What provides information regarding the ways people, teams, and organizational units behave?

    A. Organizational chart
    B. Organizational theory
    C. Organizational structure
    D. Organizational behavior

  • Question 280:

    The individual or group that provides resources and support for a project and is accountable for success is the:

    A. sponsor
    B. customer
    C. business partners
    D. functional managers

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.