  • Question 101:

    The probability and impact matrix is primarily used to:

    A. Quantify risk issues for trends during a quality audit.
    B. Develop a risk register for risk planning.
    C. Evaluate each risk's importance and priority during Perform Qualitative Risk Analysis.
    D. Define risk and compare impacts during Perform Quantitative Risk Analysis.

  • Question 102:

    Managing procurement relationships and monitoring contract performance are part of which process?

    A. Conduct Procurements
    B. Plan Procurements
    C. Administer Procurements
    D. Close Procurements

  • Question 103:

    Which of the following involves making information available to project stakeholders in a timely manner?

    A. Plan Communications
    B. Performance reporting
    C. Project status reports
    D. Distribute Information

  • Question 104:

    Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

    A. Variance Analysis
    B. Define Scope
    C. Verify Scope
    D. Control Scope

  • Question 105:

    Project contracts generally fall into which of the following three broad categories?

    A. Fixed-price, cost reimbursable, time and materials
    B. Make-or-buy, margin analysis, fixed-price
    C. Time and materials, fixed-price, margin analysis
    D. Make-or-buy, lump-sum, cost-plus-incentive

  • Question 106:

    Change requests are an output from which Project Integration Management process?

    A. Direct and Manage Project Execution
    B. Develop Project Management Plan
    C. Close Project
    D. Develop Project Charter

  • Question 107:

    Which grid shows which resources are tied to work packages?

    A. Work breakdown structure (WBS)
    B. Responsibility assignment matrix (RAM)
    C. Project assignment chart
    D. Personnel assignment matrix

  • Question 108:

    Which tool or technique is used in the Plan Scope Management process?

    A. Document analysis
    B. Observations
    C. Product analysis
    D. Expert judgment

  • Question 109:

    A disadvantage associated with virtual teams is that they:

    A. Require communication technology that is not readily available.
    B. Create difficulties when including people with disabilities.
    C. Often cannot accommodate teams that work different hours or shifts.
    D. Create the possibility for misunderstandings to arise.

  • Question 110:

    In the basic communication model, which term refers to the method that is used to convey the message?

    A. Decode
    B. Encode
    C. Medium
    D. Noise

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.