  • Question 91:

    Which of the following is an input to Control Scope?

    A. Project schedule
    B. Organizational process assets updates
    C. Project document updates
    D. Work performance information

  • Question 92:

    An output of the Perform Integrated Change Control process is:

    A. Deliverables.
    B. Validated changes.
    C. The change log.
    D. The requirements traceability matrix.

  • Question 93:

    Reserve analysis is a tool and technique used in which process?

    A. Plan Risk Management
    B. Plan Risk Responses
    C. Identify Risks
    D. Control Risks

  • Question 94:

    To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

    A. scope creep.
    B. a change request.
    C. work performance information.
    D. deliverables.

  • Question 95:

    Which Project Time Management process includes bottom-up estimating as a tool or technique?

    A. Estimate Activity Resources
    B. Sequence Activities
    C. Estimate Activity Durations
    D. Develop Schedule

  • Question 96:

    What is one of the objectives of Project Risk Management?

    A. Decrease the probability and impact of an event on project objectives.
    B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.
    C. Increase the probability and impact of positive events.
    D. Removal of project risk.

  • Question 97:

    The following is a network diagram for a project.

    The free float for Activity H is how many days?

    A. 4
    B. 5
    C. 10
    D. 11

  • Question 98:

    Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

    A. updates.
    B. defect repairs.
    C. preventive actions.
    D. corrective actions.

  • Question 99:

    The definition of operations is a/an:

    A. organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.
    B. temporary endeavor undertaken to create a unique product, service, or result.
    C. organization that provides oversight for an administrative area.
    D. organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

  • Question 100:

    Which of the following statements is true regarding project and product lifecycles?

    A. A single product lifecycle may consist of multiple project lifecycles.
    B. A product lifecycle is always shorter than the project lifecycle.
    C. A single product lifecycle can only have one project lifecycle.
    D. A single project lifecycle may consist of multiple product lifecycles.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.