What theme provides the justification for the project?
A. Quality
B. Plans
C. Progress
D. Business Case
Which is a purpose of the Initiating a Project process?
A. Decide if it is worthwhile to initiate a project
B. Decide on the project approach
C. Establish solid foundations for a project
D. Identify the number of Work Packages required
Why does PRINCE2 recommend three different levels of plans?
A. To cover initiation, specialist work and exception situations
B. To provide appropriate detail to each of the different levels of management within the project
C. As an allowance for initiation, product delivery and project closure
D. To match the different aspects of the product-based planning technique
What needs to be in place to ensure effective issue and change control?
A. Configuration management system
B. Manage by exception
C. Quality planning
D. Information needs for stakeholders
What theme defines and implements the means by which the project will verify that products meet business requirements?
A. Business Case
B. Change
C. Progress
D. Quality
Which is a Benefits Review Plan used to assess?
A. How the project's products have performed when in operational use
B. The effectiveness of the project strategies
C. The progress of the project against its plans
D. The suitability of the project management team structure and membership
Which is a true statement about time-driven controls?
A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
B. Time-driven controls take place when specific events happen
C. Time-driven controls are produced at the end of a stage
D. An Exception Report is a time-driven control
Which project characteristic suggests that projects should have a defined start and a defined end?
A. Change
B. Temporary
C. Cross-functional
D. Risk
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
A. activities
B. processes
C. products
D. quality
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
A. Executive
B. Senior User
C. Senior Supplier
D. Project Manager
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.