Which is a responsibility of the managing level within the project management team?
A. Set project tolerances
B. Approve stage completion
C. Ensure that the products are produced within the constraints agreed with the Project Board
D. Appoint the project management team
Which of the following statements about stakeholders are true?
1.
Someone who thinks they will be affected by a project is a stakeholder on that project
2.
Stakeholders may be internal or external to the corporate organization
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Which statement is FALSE?
A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B. A project's output is any of the project's specialist products
C. A project benefit is only realized after the project has closed
D. A project outcome is the result of the change derived from using the project's outputs
Which is a benefit of using PRINCE2?
A. Provides a defined structure of accountability, delegation, authority and communication
B. Includes techniques for critical path analysis and earned value analysis
C. Enables a Project Manager to be accountable for the success of a project
D. Prevents any changes once the scope of a project has been agreed
What process aims to ensure accurate progress information is provided to the Project Manager?
A. Starting up a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project
Where should an off-specification be recorded?
A. Risk Register
B. Issue Register
C. Work Package
D. Configuration Management Strategy
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
A. End Stage Report
B. Team Plan
C. Work Package
D. Project Plan
Which characteristic distinguishes a project from regular business operations?
A. Produces benefits
B. Introduces business change
C. Manages stakeholders
D. Incurs cost
Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?
A. Principles
B. Processes
C. Tailoring PRINCE2 to the project environment
D. Themes
Which should be funded by a change budget?
A. Increase in agreed scope
B. Initiation stage
C. Change Authority
D. Handover activities
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.